The SZKT large crossing tower used in the Yangtze River crossing of Three Gorges Youjing 500 kV transmission line project is constructed using combined lifting pole method,which combines guyed lifting pole and A-frame lifting pole.It solves tower construction difficulties caused by wide and heavy head of large crossing towers.This method as well as the A-frame erection and disassembling technology can be referenced for constructed wide head tower construction of the 1 000 kV UHVAC demonstration project.

About this research paper

What this paper is about

The SZKT large crossing tower used in the Yangtze River crossing of Three Gorges Youjing 500 kV transmission line project is constructed using combined lifting pole method,which combines guyed lifting pole and A-frame lifting pole.It solves tower construction difficulties caused by wide and heavy head of large crossing towers.This method as well as the A-frame erection and disassembling technology can be referenced for constructed wide head tower construction of the 1 000 kV UHVAC demonstration project.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

The SZKT large crossing tower used in the Yangtze River crossing of Three Gorges Youjing 500 kV transmission line project is constructed using combined lifting pole method,which combines guyed lifting pole and A-frame lifting pole.It solves tower construction difficulties caused by wide and heavy head of large crossing towers.This method as well as the A-frame erection and disassembling technology can be referenced for constructed wide head tower construction of the 1 000 kV UHVAC demonstration project.

Key concepts: Tower, Engineering, Three gorges, Frame (networking), Structural engineering, Head (geology), Transmission line, Electrical engineering