Case Study on Long-distance Ventilation of Zhongtianshan Tunnel Driven by TBM

Duo Shengjun

Open publisher page 0 citations

Abstract

Zhongtianshan tunnel is 22.449 km long.The 13.8 km entrance section of the tunnel is driven by TBM.Long-distance ventilation during tunneling is one of the important factors that affect the construction progress and economic efficiency.Study is made on the ventilation of Zhongtianshan tunnel on basis of the construction method,driving length and construction organization of the tunnel.Comparison and contrast is made between single-direction long-distance ventilation program and gallery-type combined ventilation program,which indicates that the gallery-type combined ventilation program is the optimum ventilation program.The stage division and number of the ventilation fans needed for the gallery-type combined ventilation program are proposed.The ventilation program is further adjusted during tunneling in accordance with the site ventilation monitoring results so as to meet the actual conditions of the site.In the end,the ventilation program adopted guarantees the successful breakthrough of Zhongtianshan tunnel.

About this research paper

What this paper is about

Zhongtianshan tunnel is 22.449 km long.The 13.8 km entrance section of the tunnel is driven by TBM.Long-distance ventilation during tunneling is one of the important factors that affect the construction progress and economic efficiency.Study is made on the ventilation of Zhongtianshan tunnel on basis of the construction method,driving length and construction organization of the tunnel.Comparison and contrast is made between single-direction long-distance ventilation program and gallery-type combined ventilation program,which indicates that the gallery-type combined ventilation program is the optimum ventilation program.The stage division and number of the ventilation fans needed for the gallery-type combined ventilation program are proposed.The ventilation program is further adjusted during tunneling in accordance with the site ventilation monitoring results so as to meet the actual conditions of the site.In the end,the ventilation program adopted guarantees the successful breakthrough of Zhongtianshan tunnel.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Zhongtianshan tunnel is 22.449 km long.The 13.8 km entrance section of the tunnel is driven by TBM.Long-distance ventilation during tunneling is one of the important factors that affect the construction progress and economic efficiency.Study is made on the ventilation of Zhongtianshan tunnel on basis of the construction method,driving length and construction organization of the tunnel.Comparison and contrast is made between single-direction long-distance ventilation program and gallery-type combined ventilation program,which indicates that the gallery-type combined ventilation program is the optimum ventilation program.The stage division and number of the ventilation fans needed for the gallery-type combined ventilation program are proposed.The ventilation program is further adjusted during tunneling in accordance with the site ventilation monitoring results so as to meet the actual conditions of the site.In the end,the ventilation program adopted guarantees the successful breakthrough of Zhongtianshan tunnel.

Key concepts: Ventilation (architecture), Engineering, Mechanical engineering

Related papers

Back to paper searchBrowse research topicsOriginal source
Case Study on Long-distance Ventilation of Zhongtianshan Tunnel Driven by TBM — Research Paper | ScholarLens