Concrete re-sleepering on the SIA

O Cheek, JE Holland

Open publisher page 0 citations

Abstract

This paper outlines the process undertaken in the planning and delivery of the program of works for the concrete re-sleepering of approximately 1.6 million sleepers on the Melbourne to Sydney lMain Southr rail corridor as part of the South Improvement Alliance. The South Improvement Alliance (SIA) is a lProgram of Worksr on the interstate standard gauge rail network between Melbourne and Sydney under an Alliance style contract with ATRC, John Holland, MVM and OrDonnell Griffin. The works involve a series of discrete packages; one of these packages is concrete re-sleepering between Melbourne and Sydney. The concrete re-sleepering program of works for the SIA consists of replacing all of the remaining sections of timber sleepered track from Melbourne to Sydney. This requires replacement of approximately 1,600,000 concrete sleepers. The indicative budget estimate for the work overall being $277 million, which equates to approximately $167 per sleeper.

About this research paper

What this paper is about

This paper outlines the process undertaken in the planning and delivery of the program of works for the concrete re-sleepering of approximately 1.6 million sleepers on the Melbourne to Sydney lMain Southr rail corridor as part of the South Improvement Alliance. The South Improvement Alliance (SIA) is a lProgram of Worksr on the interstate standard gauge rail network between Melbourne and Sydney under an Alliance style contract with ATRC, John Holland, MVM and OrDonnell Griffin. The works involve a series of discrete packages; one of these packages is concrete re-sleepering between Melbourne and Sydney. The concrete re-sleepering program of works for the SIA consists of replacing all of the remaining sections of timber sleepered track from Melbourne to Sydney. This requires replacement of approximately 1,600,000 concrete sleepers. The indicative budget estimate for the work overall being $277 million, which equates to approximately $167 per sleeper.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

This paper outlines the process undertaken in the planning and delivery of the program of works for the concrete re-sleepering of approximately 1.6 million sleepers on the Melbourne to Sydney lMain Southr rail corridor as part of the South Improvement Alliance. The South Improvement Alliance (SIA) is a lProgram of Worksr on the interstate standard gauge rail network between Melbourne and Sydney under an Alliance style contract with ATRC, John Holland, MVM and OrDonnell Griffin. The works involve a series of discrete packages; one of these packages is concrete re-sleepering between Melbourne and Sydney. The concrete re-sleepering program of works for the SIA consists of replacing all of the remaining sections of timber sleepered track from Melbourne to Sydney. This requires replacement of approximately 1,600,000 concrete sleepers. The indicative budget estimate for the work overall being $277 million, which equates to approximately $167 per sleeper.

Key concepts: Alliance, Engineering, Griffin, Work (physics), Track (disk drive), Civil engineering, Transport engineering, Archaeology

Related papers

Back to paper searchBrowse research topicsOriginal source
Concrete re-sleepering on the SIA — Research Paper | ScholarLens