1979OSTI OAI (U.S. Department of Energy Office of Scientific and Technical Information)Requires access

Bechtel completes interesting twin gas line project in Algeria

D. Dietsch

Open publisher page 0 citations

Abstract

Bechtel, Inc. has recently completed an unusual 90 km (56 miles) of dual 36-in. gas line in the gas producing area of Hassi R'mel, Algeria. The administrative requirements for custom clearance of imported materials and the logistics of hauling the pipe and materials to the job site using the Algerian nationalized transport system required a long period of time. The API 5LX grade 60 pipe, of Japanese manufacture, was delivered to the Port of Mostagenem, then hauled by truck and rail to an existing double-jointing plant located at Djelfa. After double-jointing operations were completed, the pipe was hauled by truck the remaining 230 km (143 miles) to the job site. Construction was rapidly accomplished between Jan. and April, 1979, with testing of the lines completed in June, 1979. The dual pipeline system connects 4 gas processing plants with 2 natural gas reinjection stations in the Hassi R'mel area. Construction of the pipeline required virtually all the ditch to be shot. Other requirements were asphalt coating and glass outer wrap, flood coating of field joints by hand, sand ditch padding, and a total of 38 pieces of heavy construction equipment.

About this research paper

What this paper is about

Bechtel, Inc. has recently completed an unusual 90 km (56 miles) of dual 36-in. gas line in the gas producing area of Hassi R'mel, Algeria. The administrative requirements for custom clearance of imported materials and the logistics of hauling the pipe and materials to the job site using the Algerian nationalized transport system required a long period of time. The API 5LX grade 60 pipe, of Japanese manufacture, was delivered to the Port of Mostagenem, then hauled by truck and rail to an existing double-jointing plant located at Djelfa. After double-jointing operations were completed, the pipe was hauled by truck the remaining 230 km (143 miles) to the job site. Construction was rapidly accomplished between Jan. and April, 1979, with testing of the lines completed in June, 1979. The dual pipeline system connects 4 gas processing plants with 2 natural gas reinjection stations in the Hassi R'mel area. Construction of the pipeline required virtually all the ditch to be shot. Other requirements were asphalt coating and glass outer wrap, flood coating of field joints by hand, sand ditch padding, and a total of 38 pieces of heavy construction equipment.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Bechtel, Inc. has recently completed an unusual 90 km (56 miles) of dual 36-in. gas line in the gas producing area of Hassi R'mel, Algeria. The administrative requirements for custom clearance of imported materials and the logistics of hauling the pipe and materials to the job site using the Algerian nationalized transport system required a long period of time. The API 5LX grade 60 pipe, of Japanese manufacture, was delivered to the Port of Mostagenem, then hauled by truck and rail to an existing double-jointing plant located at Djelfa. After double-jointing operations were completed, the pipe was hauled by truck the remaining 230 km (143 miles) to the job site. Construction was rapidly accomplished between Jan. and April, 1979, with testing of the lines completed in June, 1979. The dual pipeline system connects 4 gas processing plants with 2 natural gas reinjection stations in the Hassi R'mel area. Construction of the pipeline required virtually all the ditch to be shot. Other requirements were asphalt coating and glass outer wrap, flood coating of field joints by hand, sand ditch padding, and a total of 38 pieces of heavy construction equipment.

Key concepts: Ditch, Truck, Natural gas, Port (circuit theory), Trailer, Engineering, Pipeline transport, Natural gas field

Related papers

Back to paper searchBrowse research topicsOriginal source
Bechtel completes interesting twin gas line project in Algeria — Research Paper | ScholarLens