Guatemala switch to crude saves over $1 million a month
V. de Biasi
Abstract
V. de Biasi
Abstract
In a two-step program designed to reduce fuel costs and improve operating efficiency, Empresa Electrica de Guatemala has modified two General Electric PG 5341 gas turbines at Laguna to run on crude oil and installed heat recovery equipment for repowering two existing steam turbines. The gas turbines, nominally rated at around 19,000 kW for base load operation at 70/sup 0/F average ambient temperature and 4000 feet altitude, were installed in 1977-78 as a base load backup to hydro power during the dry season. Original plan was to put them into immediate service as simple cycle units and then convert to combined cycle operation. Priorities were shifted to switch over from distillate to crude oil firing before going ahead with the combined cycle istallation. Their economic evaluation showed the initial investment would be paid off in a few months by the savings in fuel costs.
A significance statement is not available in the OpenAlex record.
A contribution statement is not available in the OpenAlex record.
Method details are not available in the OpenAlex metadata.
Findings are not separately available in the OpenAlex metadata.
Limitations are not available in the OpenAlex metadata.
Application details are not available in the OpenAlex metadata.
In a two-step program designed to reduce fuel costs and improve operating efficiency, Empresa Electrica de Guatemala has modified two General Electric PG 5341 gas turbines at Laguna to run on crude oil and installed heat recovery equipment for repowering two existing steam turbines. The gas turbines, nominally rated at around 19,000 kW for base load operation at 70/sup 0/F average ambient temperature and 4000 feet altitude, were installed in 1977-78 as a base load backup to hydro power during the dry season. Original plan was to put them into immediate service as simple cycle units and then convert to combined cycle operation. Priorities were shifted to switch over from distillate to crude oil firing before going ahead with the combined cycle istallation. Their economic evaluation showed the initial investment would be paid off in a few months by the savings in fuel costs.
Key concepts: Backup, Environmental science, Investment (military), Combined cycle, Gas turbines, Crude oil, Electric power, Engineering