Construction diversion tunnel(in combination with tailrace tunnel) design of Xiluodu Hydropower Station

Yun Qiu

Open publisher page 0 citations

Abstract

Xiluodu Hydropower Station is the largest one on the Jinshajiang river.3 diversion tunnels symmetrical arrangement in each abut ment,in which No.1,No.2,No.5,No.6 diversion tunnel are combined with the tailrace tunnel.Each tunnel has a flow cross-section of 18m×20m(width×height),the largest excavated section reaches 21.60m×23.60m.Besides the low angle interlayer-intraformational shear zones endanger the tunnel crown surrounding rock stability,the tunnel working condition is complicated the design and construction of large-diameter diversion tunnels call for high requirements of design concept and technology.

About this research paper

What this paper is about

Xiluodu Hydropower Station is the largest one on the Jinshajiang river.3 diversion tunnels symmetrical arrangement in each abut ment,in which No.1,No.2,No.5,No.6 diversion tunnel are combined with the tailrace tunnel.Each tunnel has a flow cross-section of 18m×20m(width×height),the largest excavated section reaches 21.60m×23.60m.Besides the low angle interlayer-intraformational shear zones endanger the tunnel crown surrounding rock stability,the tunnel working condition is complicated the design and construction of large-diameter diversion tunnels call for high requirements of design concept and technology.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Xiluodu Hydropower Station is the largest one on the Jinshajiang river.3 diversion tunnels symmetrical arrangement in each abut ment,in which No.1,No.2,No.5,No.6 diversion tunnel are combined with the tailrace tunnel.Each tunnel has a flow cross-section of 18m×20m(width×height),the largest excavated section reaches 21.60m×23.60m.Besides the low angle interlayer-intraformational shear zones endanger the tunnel crown surrounding rock stability,the tunnel working condition is complicated the design and construction of large-diameter diversion tunnels call for high requirements of design concept and technology.

Key concepts: Hydropower, Water diversion, Geotechnical engineering, Geology, Section (typography), Engineering, Environmental science, Business

Related papers

Back to paper searchBrowse research topicsOriginal source
Construction diversion tunnel(in combination with tailrace tunnel) design of Xiluodu Hydropower Station — Research Paper | ScholarLens