Design and Construction Technology of Bored Pile in a Wharf in Republic of Liberia

Li K

Open publisher page 0 citations

Abstract

A wharf reconstruction project lies in Monrovia,Republic of Liberia,where the silt and silt clay formations are thick with high compressibility and thixotropic. Considering the factors of stratum conditions,construction equipments,project period and project cost,the bored pile is designed according to the related standard and according to the site conditions and the characteristics of the bored grouting pile,and the construction process is formulated. The quality control measures are put forward for the problems of water oozing from casing,drilling tool sticking and grouting pipe blocking in bored grouting pile construction.

About this research paper

What this paper is about

A wharf reconstruction project lies in Monrovia,Republic of Liberia,where the silt and silt clay formations are thick with high compressibility and thixotropic. Considering the factors of stratum conditions,construction equipments,project period and project cost,the bored pile is designed according to the related standard and according to the site conditions and the characteristics of the bored grouting pile,and the construction process is formulated. The quality control measures are put forward for the problems of water oozing from casing,drilling tool sticking and grouting pipe blocking in bored grouting pile construction.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

A wharf reconstruction project lies in Monrovia,Republic of Liberia,where the silt and silt clay formations are thick with high compressibility and thixotropic. Considering the factors of stratum conditions,construction equipments,project period and project cost,the bored pile is designed according to the related standard and according to the site conditions and the characteristics of the bored grouting pile,and the construction process is formulated. The quality control measures are put forward for the problems of water oozing from casing,drilling tool sticking and grouting pipe blocking in bored grouting pile construction.

Key concepts: Wharf, Pile, Casing, Silt, Geotechnical engineering, Engineering, Thixotropy, Drilling