2013ForecastingOpen access

Research on Improved Method for Project Performance Evaluation Based on Earned Value Management

Liwen Chen

Open full text 2 citations

Abstract

Through literature review and field research,we found that the traditional project earned value method is based on overall angle to evaluate project schedule performance.Meanwhile,this method also doesn’t distinguish the earned value which is from critical path activities or non-critical path activities.Traditional project earned value method is based on the assumption of constant project completion time.When using traditional project earned value method to evaluate project schedule performance and cost performance,easy to cause discrepancy appearance between the schedule and cost performance monitoring results and the practical results.In this paper,analyzed the defects of traditional project earned value method through actual examples,and put forward an improved project performance evaluation method based on activities and key path perspectives.Finally,we introduced a case to verify the validity of improved method.

About this research paper

What this paper is about

Through literature review and field research,we found that the traditional project earned value method is based on overall angle to evaluate project schedule performance.Meanwhile,this method also doesn’t distinguish the earned value which is from critical path activities or non-critical path activities.Traditional project earned value method is based on the assumption of constant project completion time.When using traditional project earned value method to evaluate project schedule performance and cost performance,easy to cause discrepancy appearance between the schedule and cost performance monitoring results and the practical results.In this paper,analyzed the defects of traditional project earned value method through actual examples,and put forward an improved project performance evaluation method based on activities and key path perspectives.Finally,we introduced a case to verify the validity of improved method.

Why it matters

OpenAlex reports 2 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Through literature review and field research,we found that the traditional project earned value method is based on overall angle to evaluate project schedule performance.Meanwhile,this method also doesn’t distinguish the earned value which is from critical path activities or non-critical path activities.Traditional project earned value method is based on the assumption of constant project completion time.When using traditional project earned value method to evaluate project schedule performance and cost performance,easy to cause discrepancy appearance between the schedule and cost performance monitoring results and the practical results.In this paper,analyzed the defects of traditional project earned value method through actual examples,and put forward an improved project performance evaluation method based on activities and key path perspectives.Finally,we introduced a case to verify the validity of improved method.

Key concepts: Earned value management, Critical path method, Schedule, Project management, Computer science, Operations research, Value (mathematics), Project planning