Analysis on construction efficiency of shield machine in tunnel crossing Yellow River of middle route project of S-N water diversion

Qinghong Wu

Open publisher page 0 citations

Abstract

In order to analyze the construction efficiency of shield machine and improve accuracy of calculating the unit price of shield machine construction,based on the practical condition and related data,and further according to the basic principle of control chart,the reasonable upper controlling line and lower controlling line were set up to filter out the abnormal data.The construction efficiencies of shield machine construction in different geological conditions and cases were analyzed tentatively.Therefore,the basic data and related experiences were provided for correctly predicting and controlling the investment of similar works.

About this research paper

What this paper is about

In order to analyze the construction efficiency of shield machine and improve accuracy of calculating the unit price of shield machine construction,based on the practical condition and related data,and further according to the basic principle of control chart,the reasonable upper controlling line and lower controlling line were set up to filter out the abnormal data.The construction efficiencies of shield machine construction in different geological conditions and cases were analyzed tentatively.Therefore,the basic data and related experiences were provided for correctly predicting and controlling the investment of similar works.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

In order to analyze the construction efficiency of shield machine and improve accuracy of calculating the unit price of shield machine construction,based on the practical condition and related data,and further according to the basic principle of control chart,the reasonable upper controlling line and lower controlling line were set up to filter out the abnormal data.The construction efficiencies of shield machine construction in different geological conditions and cases were analyzed tentatively.Therefore,the basic data and related experiences were provided for correctly predicting and controlling the investment of similar works.

Key concepts: Shield, Chart, Line (geometry), Filter (signal processing), Set (abstract data type), Tunnel construction, Computer science, Investment (military)

Related papers

Back to paper searchBrowse research topicsOriginal source
Analysis on construction efficiency of shield machine in tunnel crossing Yellow River of middle route project of S-N water diversion — Research Paper | ScholarLens