2012Journal of Beijing University of Civil Engineering and ArchitectureRequires access

Research on Key Technology of Lifting and Splicing Construction Control for Long-Span Composite Steel and Concrete Beam Bridge

Bucea Beijing

Open publisher page 0 citations

Abstract

To solve the problem of construction method without scaffolding to across certain obstacles,the cantilever installation construction method of steel-concrete composite beam bridge is put forward.The key technology of this method is the precision and safety controls.In the process of cantilever installation of the steel box girder,therefore,the installation locators is designed,and the preliminary positioning of the box girder and the safety requirements is achieved.According to the accuracy requirement,and after that the system theory analysis,the general formula for corner control values of the spliced face of steel box shaped girder and the axial deformations of environmental temperature regulating value is derived theoretically,and the technical support for cantilever installation precision of long span variable section steel box shaped continuous girder bridges is provided.In the solution of construction process without scaffolding to across certain obstacles,this method shows the quality of fast,safe and practical,and it has general application value.

About this research paper

What this paper is about

To solve the problem of construction method without scaffolding to across certain obstacles,the cantilever installation construction method of steel-concrete composite beam bridge is put forward.The key technology of this method is the precision and safety controls.In the process of cantilever installation of the steel box girder,therefore,the installation locators is designed,and the preliminary positioning of the box girder and the safety requirements is achieved.According to the accuracy requirement,and after that the system theory analysis,the general formula for corner control values of the spliced face of steel box shaped girder and the axial deformations of environmental temperature regulating value is derived theoretically,and the technical support for cantilever installation precision of long span variable section steel box shaped continuous girder bridges is provided.In the solution of construction process without scaffolding to across certain obstacles,this method shows the quality of fast,safe and practical,and it has general application value.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

To solve the problem of construction method without scaffolding to across certain obstacles,the cantilever installation construction method of steel-concrete composite beam bridge is put forward.The key technology of this method is the precision and safety controls.In the process of cantilever installation of the steel box girder,therefore,the installation locators is designed,and the preliminary positioning of the box girder and the safety requirements is achieved.According to the accuracy requirement,and after that the system theory analysis,the general formula for corner control values of the spliced face of steel box shaped girder and the axial deformations of environmental temperature regulating value is derived theoretically,and the technical support for cantilever installation precision of long span variable section steel box shaped continuous girder bridges is provided.In the solution of construction process without scaffolding to across certain obstacles,this method shows the quality of fast,safe and practical,and it has general application value.

Key concepts: Cantilever, Box girder, Structural engineering, Span (engineering), Bridge (graph theory), Engineering, Beam (structure), Process (computing)