Excavation Technology for Dam Foundation of Dahuashui Hydropower Station

Hongying Yuan

Open publisher page 0 citations

Abstract

There are high slopes with angle of 70° on both of dam abutments of Dahuashui hydropower Station.Under the condition that large-scale construction machines could not be used,submerged and hand drills are mainly used for excavation of abutments.Excavation of inclined bench with angle of 35°∽45°was adopted resulting in that ballast can automatically roll down into foundation ditch after explosion.When the arch dam foundation ditch is excavated,large-scale machines are adopted.This technology could ensure construction schedule.

About this research paper

What this paper is about

There are high slopes with angle of 70° on both of dam abutments of Dahuashui hydropower Station.Under the condition that large-scale construction machines could not be used,submerged and hand drills are mainly used for excavation of abutments.Excavation of inclined bench with angle of 35°∽45°was adopted resulting in that ballast can automatically roll down into foundation ditch after explosion.When the arch dam foundation ditch is excavated,large-scale machines are adopted.This technology could ensure construction schedule.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

There are high slopes with angle of 70° on both of dam abutments of Dahuashui hydropower Station.Under the condition that large-scale construction machines could not be used,submerged and hand drills are mainly used for excavation of abutments.Excavation of inclined bench with angle of 35°∽45°was adopted resulting in that ballast can automatically roll down into foundation ditch after explosion.When the arch dam foundation ditch is excavated,large-scale machines are adopted.This technology could ensure construction schedule.

Key concepts: Excavation, Foundation (evidence), Ditch, Hydropower, Engineering, Arch dam, Geotechnical engineering, Abutment