Leakage analysis and retrofitting plan of economizers in 420 t/h boilers in Lianzhou Power Plant

Jian Yang

Open publisher page 0 citations

Abstract

The leakage of the economizers in 420 t/h boilers in Lianzhou Power Plant becomes very severe after twoodd years service of the boilers.This paper analyzes the causes of the leakage,putting emphasis on the effects of flue gas velocity,fly ash concentration and heating surface layout,etc.on the abrasion of the economizers.According to the circumstances of the plant,the use of the membrane type economizer is suggested as a solution,and specific retrofitting plan is given.

About this research paper

What this paper is about

The leakage of the economizers in 420 t/h boilers in Lianzhou Power Plant becomes very severe after twoodd years service of the boilers.This paper analyzes the causes of the leakage,putting emphasis on the effects of flue gas velocity,fly ash concentration and heating surface layout,etc.on the abrasion of the economizers.According to the circumstances of the plant,the use of the membrane type economizer is suggested as a solution,and specific retrofitting plan is given.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

The leakage of the economizers in 420 t/h boilers in Lianzhou Power Plant becomes very severe after twoodd years service of the boilers.This paper analyzes the causes of the leakage,putting emphasis on the effects of flue gas velocity,fly ash concentration and heating surface layout,etc.on the abrasion of the economizers.According to the circumstances of the plant,the use of the membrane type economizer is suggested as a solution,and specific retrofitting plan is given.

Key concepts: Economizer, Retrofitting, Power station, Flue gas, Waste management, Fly ash, Engineering, Leakage (economics)