Pre-splitting blasting technology for foundation excavation of high RCC double-curvature thin arch dam

Zhang Yao-wei

Open publisher page 0 citations

Abstract

Under the consideration of the engineering geological condition of Dahuashui Hydropower Station,the pre-splitting blasting technology and reasonable construction method are adopted for the excavation of the dam foundation in accordance with the analysis on the rock strata therein,in which the design of the blasting parameters and powder charging structure as well as the angle control and the height of the excavating steps are particularly determined,and then better splitting effect is got for the slope excavation and the quality requirement of the construction is satisfied as well.

About this research paper

What this paper is about

Under the consideration of the engineering geological condition of Dahuashui Hydropower Station,the pre-splitting blasting technology and reasonable construction method are adopted for the excavation of the dam foundation in accordance with the analysis on the rock strata therein,in which the design of the blasting parameters and powder charging structure as well as the angle control and the height of the excavating steps are particularly determined,and then better splitting effect is got for the slope excavation and the quality requirement of the construction is satisfied as well.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Under the consideration of the engineering geological condition of Dahuashui Hydropower Station,the pre-splitting blasting technology and reasonable construction method are adopted for the excavation of the dam foundation in accordance with the analysis on the rock strata therein,in which the design of the blasting parameters and powder charging structure as well as the angle control and the height of the excavating steps are particularly determined,and then better splitting effect is got for the slope excavation and the quality requirement of the construction is satisfied as well.

Key concepts: Excavation, Arch dam, Foundation (evidence), Rock blasting, Arch, Geotechnical engineering, Hydropower, Engineering