Non-boring operation of TBM in Dahuofang tunnel project

DU Shi-bi

Open publisher page 0 citations

Abstract

The paper puts forward the concept of non-boring operation of TBM,which is often in the straight line schedule of tunnel construction.The practice of Dahuofang tunnel project shows that the time of the non-boring operation has the high percentage in the boring operation time,up to 83% on average.Therefore,the non-boring operation should be considered fully to make the scientific and reasonable construction planning in design and construction to the tunnel project with TBM.

About this research paper

What this paper is about

The paper puts forward the concept of non-boring operation of TBM,which is often in the straight line schedule of tunnel construction.The practice of Dahuofang tunnel project shows that the time of the non-boring operation has the high percentage in the boring operation time,up to 83% on average.Therefore,the non-boring operation should be considered fully to make the scientific and reasonable construction planning in design and construction to the tunnel project with TBM.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

The paper puts forward the concept of non-boring operation of TBM,which is often in the straight line schedule of tunnel construction.The practice of Dahuofang tunnel project shows that the time of the non-boring operation has the high percentage in the boring operation time,up to 83% on average.Therefore,the non-boring operation should be considered fully to make the scientific and reasonable construction planning in design and construction to the tunnel project with TBM.

Key concepts: Schedule, Engineering, Construction engineering, Civil engineering, Tunnel construction, Forensic engineering, Geotechnical engineering, Computer science