2001Civil engineeringRequires access

Extended Life Span

Roan Stamm, David Marcic, H. Everett Drugge

Open publisher page 2 citations

Abstract

The Harlem River Lift Span—part of New York City's Triborough Bridge System—was the largest vertical span in the country at the time of its construction in 1936. The lift span is 310 ft (94 m) long and when closed, it provides a 55-ft (16.8 m) clearance above the river. The bridge also includes two through-truss spans and two tower spans, for a total length of 770 ft (235 m), bringing the Harlem River Lift Span into compliance with current standards required, increasing its live-load capacity, replacing its deck, protecting its piers from vessel collisions, and adding seismic isolation bearings. The designers recommended a new steel battle deck for the entire bridge and the approach spans, in conjunction with the strengthening of four substandard floor beams, to improve the bridge's load rating without increasing the weight of the deck. Along with the deck replacement, the overall roadway geometry is to be improved, with the six existing 10 ft 2 in. (3.1 m) wide lanes widened to 10 ft 6 in. (3.2 m) by decreasing the shoulder width from 1 ft 6 in. (0.46 m) to 1 ft (0.30 m). Additionally, a reinforced-concrete pier protection system will be installed in the form of a continuous concrete rim beam supported on concrete piles that will be embedded in rock below the river bottom.

About this research paper

What this paper is about

The Harlem River Lift Span—part of New York City's Triborough Bridge System—was the largest vertical span in the country at the time of its construction in 1936. The lift span is 310 ft (94 m) long and when closed, it provides a 55-ft (16.8 m) clearance above the river. The bridge also includes two through-truss spans and two tower spans, for a total length of 770 ft (235 m), bringing the Harlem River Lift Span into compliance with current standards required, increasing its live-load capacity, replacing its deck, protecting its piers from vessel collisions, and adding seismic isolation bearings. The designers recommended a new steel battle deck for the entire bridge and the approach spans, in conjunction with the strengthening of four substandard floor beams, to improve the bridge's load rating without increasing the weight of the deck. Along with the deck replacement, the overall roadway geometry is to be improved, with the six existing 10 ft 2 in. (3.1 m) wide lanes widened to 10 ft 6 in. (3.2 m) by decreasing the shoulder width from 1 ft 6 in. (0.46 m) to 1 ft (0.30 m). Additionally, a reinforced-concrete pier protection system will be installed in the form of a continuous concrete rim beam supported on concrete piles that will be embedded in rock below the river bottom.

Why it matters

OpenAlex reports 2 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

The Harlem River Lift Span—part of New York City's Triborough Bridge System—was the largest vertical span in the country at the time of its construction in 1936. The lift span is 310 ft (94 m) long and when closed, it provides a 55-ft (16.8 m) clearance above the river. The bridge also includes two through-truss spans and two tower spans, for a total length of 770 ft (235 m), bringing the Harlem River Lift Span into compliance with current standards required, increasing its live-load capacity, replacing its deck, protecting its piers from vessel collisions, and adding seismic isolation bearings. The designers recommended a new steel battle deck for the entire bridge and the approach spans, in conjunction with the strengthening of four substandard floor beams, to improve the bridge's load rating without increasing the weight of the deck. Along with the deck replacement, the overall roadway geometry is to be improved, with the six existing 10 ft 2 in. (3.1 m) wide lanes widened to 10 ft 6 in. (3.2 m) by decreasing the shoulder width from 1 ft 6 in. (0.46 m) to 1 ft (0.30 m). Additionally, a reinforced-concrete pier protection system will be installed in the form of a continuous concrete rim beam supported on concrete piles that will be embedded in rock below the river bottom.

Key concepts: Span (engineering), Deck, Structural engineering, Beam bridge, Pier, Engineering, Lift (data mining), Bridge (graph theory)