FRIARTON BRIDGE REACHES OUT FOR THE FINISHING LINE

Sue A. Wade

Open publisher page 0 citations

Abstract

Details are given of the Friarton Bridge, Perth, to be opened in September 1978. The opening is over a year behind schedule. Reasons for the delay are said to be unexpected ground conditions, bad weather, strikes, and late steel deliveries. The main river span of the 831 M bridge is 174 M long - flanked on each side by anchor spans of 114 M with 4 remaining spans of 75 M, plus one 66 M span at the north abutment and one 63 M span at the south. The superstructure consists of 2 independent steel box girders each supporting a lightweight reinforced concrete road deck separated by a 100 mm gap. Design problems were greatly simplified by dividing the deck along the centre of the median and effectively building 2 side by side box girder bridges. /TRRL/

About this research paper

What this paper is about

Details are given of the Friarton Bridge, Perth, to be opened in September 1978. The opening is over a year behind schedule. Reasons for the delay are said to be unexpected ground conditions, bad weather, strikes, and late steel deliveries. The main river span of the 831 M bridge is 174 M long - flanked on each side by anchor spans of 114 M with 4 remaining spans of 75 M, plus one 66 M span at the north abutment and one 63 M span at the south. The superstructure consists of 2 independent steel box girders each supporting a lightweight reinforced concrete road deck separated by a 100 mm gap. Design problems were greatly simplified by dividing the deck along the centre of the median and effectively building 2 side by side box girder bridges. /TRRL/

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Details are given of the Friarton Bridge, Perth, to be opened in September 1978. The opening is over a year behind schedule. Reasons for the delay are said to be unexpected ground conditions, bad weather, strikes, and late steel deliveries. The main river span of the 831 M bridge is 174 M long - flanked on each side by anchor spans of 114 M with 4 remaining spans of 75 M, plus one 66 M span at the north abutment and one 63 M span at the south. The superstructure consists of 2 independent steel box girders each supporting a lightweight reinforced concrete road deck separated by a 100 mm gap. Design problems were greatly simplified by dividing the deck along the centre of the median and effectively building 2 side by side box girder bridges. /TRRL/

Key concepts: Deck, Span (engineering), Structural engineering, Box girder, Girder, Precast concrete, Bridge (graph theory), Beam bridge