Blasting in the North Shore driven tunnels

R H Nowotny, P Kohout

Open publisher page 0 citations

Abstract

Seventeen metres below one of Australia's premier residential areas, Thiess Thyssen North Shore Tunnels Joint Venture is driving two land tunnels. The tunnels are being driven using a combination of drill and blast and mechanical methods. The primary method of excavation is by drill and blast and because of the sensitivity of the area and the licence conditions enforced by the State Pollution Control Commission all aspects of this method must be strictly controlled and monitored. The areas of discussion are the design work leading up to the commencement of blasting, the various changes made in the blast design to comply with the licence conditions, blast monitoring and the use of various explosives products (A).

About this research paper

What this paper is about

Seventeen metres below one of Australia's premier residential areas, Thiess Thyssen North Shore Tunnels Joint Venture is driving two land tunnels. The tunnels are being driven using a combination of drill and blast and mechanical methods. The primary method of excavation is by drill and blast and because of the sensitivity of the area and the licence conditions enforced by the State Pollution Control Commission all aspects of this method must be strictly controlled and monitored. The areas of discussion are the design work leading up to the commencement of blasting, the various changes made in the blast design to comply with the licence conditions, blast monitoring and the use of various explosives products (A).

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Seventeen metres below one of Australia's premier residential areas, Thiess Thyssen North Shore Tunnels Joint Venture is driving two land tunnels. The tunnels are being driven using a combination of drill and blast and mechanical methods. The primary method of excavation is by drill and blast and because of the sensitivity of the area and the licence conditions enforced by the State Pollution Control Commission all aspects of this method must be strictly controlled and monitored. The areas of discussion are the design work leading up to the commencement of blasting, the various changes made in the blast design to comply with the licence conditions, blast monitoring and the use of various explosives products (A).

Key concepts: Drilling and blasting, Drill, Rock blasting, Shore, Excavation, Detonator, Explosive material, Mining engineering