TROUBLED WATER FOR BALLACHULISH BRIDGE

J Gosney

Open publisher page 0 citations

Abstract

This brief article describes the method used to replace a 1.5M dia., 2500 ton capacity bridge bearing which failed at the Ballachulish bridge over Loch Leven, Scotland. The trouble occurred at the south pier and the article describes the jacking procedures used to raise the deck off the pier and which were complicated by the presence of 18 rock anchors used to resist uplift of the span at that point. Much strengthening of the deck was required before jacking was successfully accomplished using four 1000 ton capacity jacks. The article states that tests are being carried out on the remaining three bearings in the bridge in order to assess their condition. /TRRL/

About this research paper

What this paper is about

This brief article describes the method used to replace a 1.5M dia., 2500 ton capacity bridge bearing which failed at the Ballachulish bridge over Loch Leven, Scotland. The trouble occurred at the south pier and the article describes the jacking procedures used to raise the deck off the pier and which were complicated by the presence of 18 rock anchors used to resist uplift of the span at that point. Much strengthening of the deck was required before jacking was successfully accomplished using four 1000 ton capacity jacks. The article states that tests are being carried out on the remaining three bearings in the bridge in order to assess their condition. /TRRL/

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

This brief article describes the method used to replace a 1.5M dia., 2500 ton capacity bridge bearing which failed at the Ballachulish bridge over Loch Leven, Scotland. The trouble occurred at the south pier and the article describes the jacking procedures used to raise the deck off the pier and which were complicated by the presence of 18 rock anchors used to resist uplift of the span at that point. Much strengthening of the deck was required before jacking was successfully accomplished using four 1000 ton capacity jacks. The article states that tests are being carried out on the remaining three bearings in the bridge in order to assess their condition. /TRRL/

Key concepts: Jacking, Pier, Engineering, Bridge (graph theory), Deck, Bridge deck, Forensic engineering, Geotechnical engineering

Related papers

Back to paper searchBrowse research topicsOriginal source
TROUBLED WATER FOR BALLACHULISH BRIDGE — Research Paper | ScholarLens