CONCRETE PAVEMENT REPLACED IN 1-1/2 HOURS

J E Simonsen

Open publisher page 0 citations

Abstract

IN ORDER TO FIND A LASTING CONCRETE PAVEMENT REPAIR THAT WOULD REDUCE LANE CLOSURE TIME TO A MINIMUM, MICHIGAN HAS DEVELOPED TWO PROCEDURES TO DATE: PRECAST SLAB REPAIRS, AND REPAIRS WITH FAST-SETTING CONCRETE. A PREVIOUSLY SAWED 10 BY 12-FOOT CONCRETE AREA CAN BE REMOVED AND REPLACED WITH A PRECAST SLAB AND OPEN TO TRAFFIC IN APPROXIMATELY 1-1/2 HOURS. A REPAIR WITH FAST-SETTING CONCRETE CAN BE SUBJECTED TO TRAFFIC ABOUT SIX HOURS AFTER POURING. THE LIMITS OF THE FAILED AREA ARE SAWED FULL-DEPTH AND THE CONCRETE IS REMOVED WITHOUT DISTURBING THE EXISTING BASE. JOINTS BETWEEN THE OLD AND NEW SLAB MAY BE DOWELED OR UNDOWELED, AND CAN BE EITHER CONTRACTION OR EXPANSION JOINTS. EVALUATION TO DATE INDICATES THAT THE REPAIRS ARE PERFORMING SATISFACTORILY. (AUTHOR)

About this research paper

What this paper is about

IN ORDER TO FIND A LASTING CONCRETE PAVEMENT REPAIR THAT WOULD REDUCE LANE CLOSURE TIME TO A MINIMUM, MICHIGAN HAS DEVELOPED TWO PROCEDURES TO DATE: PRECAST SLAB REPAIRS, AND REPAIRS WITH FAST-SETTING CONCRETE. A PREVIOUSLY SAWED 10 BY 12-FOOT CONCRETE AREA CAN BE REMOVED AND REPLACED WITH A PRECAST SLAB AND OPEN TO TRAFFIC IN APPROXIMATELY 1-1/2 HOURS. A REPAIR WITH FAST-SETTING CONCRETE CAN BE SUBJECTED TO TRAFFIC ABOUT SIX HOURS AFTER POURING. THE LIMITS OF THE FAILED AREA ARE SAWED FULL-DEPTH AND THE CONCRETE IS REMOVED WITHOUT DISTURBING THE EXISTING BASE. JOINTS BETWEEN THE OLD AND NEW SLAB MAY BE DOWELED OR UNDOWELED, AND CAN BE EITHER CONTRACTION OR EXPANSION JOINTS. EVALUATION TO DATE INDICATES THAT THE REPAIRS ARE PERFORMING SATISFACTORILY. (AUTHOR)

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

IN ORDER TO FIND A LASTING CONCRETE PAVEMENT REPAIR THAT WOULD REDUCE LANE CLOSURE TIME TO A MINIMUM, MICHIGAN HAS DEVELOPED TWO PROCEDURES TO DATE: PRECAST SLAB REPAIRS, AND REPAIRS WITH FAST-SETTING CONCRETE. A PREVIOUSLY SAWED 10 BY 12-FOOT CONCRETE AREA CAN BE REMOVED AND REPLACED WITH A PRECAST SLAB AND OPEN TO TRAFFIC IN APPROXIMATELY 1-1/2 HOURS. A REPAIR WITH FAST-SETTING CONCRETE CAN BE SUBJECTED TO TRAFFIC ABOUT SIX HOURS AFTER POURING. THE LIMITS OF THE FAILED AREA ARE SAWED FULL-DEPTH AND THE CONCRETE IS REMOVED WITHOUT DISTURBING THE EXISTING BASE. JOINTS BETWEEN THE OLD AND NEW SLAB MAY BE DOWELED OR UNDOWELED, AND CAN BE EITHER CONTRACTION OR EXPANSION JOINTS. EVALUATION TO DATE INDICATES THAT THE REPAIRS ARE PERFORMING SATISFACTORILY. (AUTHOR)

Key concepts: Precast concrete, Slab, Structural engineering, Closure (psychology), Geotechnical engineering, Forensic engineering, Engineering, Geology

Related papers

Back to paper searchBrowse research topicsOriginal source
CONCRETE PAVEMENT REPLACED IN 1-1/2 HOURS — Research Paper | ScholarLens