HOW TO REDUCE TO A MINIMUM THE COST OF EARTHWORKS WITH A GIVEN PROFILE

G Meulemans

Open publisher page 0 citations

Abstract

The optlon computer program plans earthworks at a minimum cost by selecting the optimum combination of earthwork balance and types of earthmoving equipment. The data required are the location and volumes of cuttings and fills, the location and capacity of borrow sites, and the costs of the various earthmoving operations with the different types of earth moving machinery available. The results obtained give the volume, origin and destination of all earthworks movements, type of machine to use and total earthworks costs. /TRRL/

About this research paper

What this paper is about

The optlon computer program plans earthworks at a minimum cost by selecting the optimum combination of earthwork balance and types of earthmoving equipment. The data required are the location and volumes of cuttings and fills, the location and capacity of borrow sites, and the costs of the various earthmoving operations with the different types of earth moving machinery available. The results obtained give the volume, origin and destination of all earthworks movements, type of machine to use and total earthworks costs. /TRRL/

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

The optlon computer program plans earthworks at a minimum cost by selecting the optimum combination of earthwork balance and types of earthmoving equipment. The data required are the location and volumes of cuttings and fills, the location and capacity of borrow sites, and the costs of the various earthmoving operations with the different types of earth moving machinery available. The results obtained give the volume, origin and destination of all earthworks movements, type of machine to use and total earthworks costs. /TRRL/

Key concepts: Earthworks, Engineering, Civil engineering, Geotechnical engineering