Optimizing earthwork estimating for highway construction

Felix Thomas Uhlik

Open publisher page 1 citations

Abstract

The purpose of this research was to advance the state-of-the-art in earthwork estimating of highway projects. The thesis concentrated on the uncertainties associated with calculating the quantity of rock in cut areas, estimating the fleet production, and selecting the optimum distribution of material between cut and fill areas. Estimation of the quantity of rock was achieved by using change-constrained linear programming -- a technique that allows the user to transform stochastic quantity constraints into deterministic ones. The system was applied to a highway project in Pennsylvania, and the proposed system was compared with other more traditional estimating methods. The conclusions reflect the fact that, although probabilistic estimating is in its infancy, it has great potential for reducing the risk and increasing the profits of earthwork contractors.

About this research paper

What this paper is about

The purpose of this research was to advance the state-of-the-art in earthwork estimating of highway projects. The thesis concentrated on the uncertainties associated with calculating the quantity of rock in cut areas, estimating the fleet production, and selecting the optimum distribution of material between cut and fill areas. Estimation of the quantity of rock was achieved by using change-constrained linear programming -- a technique that allows the user to transform stochastic quantity constraints into deterministic ones. The system was applied to a highway project in Pennsylvania, and the proposed system was compared with other more traditional estimating methods. The conclusions reflect the fact that, although probabilistic estimating is in its infancy, it has great potential for reducing the risk and increasing the profits of earthwork contractors.

Why it matters

OpenAlex reports 1 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

The purpose of this research was to advance the state-of-the-art in earthwork estimating of highway projects. The thesis concentrated on the uncertainties associated with calculating the quantity of rock in cut areas, estimating the fleet production, and selecting the optimum distribution of material between cut and fill areas. Estimation of the quantity of rock was achieved by using change-constrained linear programming -- a technique that allows the user to transform stochastic quantity constraints into deterministic ones. The system was applied to a highway project in Pennsylvania, and the proposed system was compared with other more traditional estimating methods. The conclusions reflect the fact that, although probabilistic estimating is in its infancy, it has great potential for reducing the risk and increasing the profits of earthwork contractors.

Key concepts: Earthworks, Estimation, Probabilistic logic, Linear programming, Engineering, Computer science, Civil engineering, Operations research