TRAFFIC SIGNAL CONTROL OF ROUNDABOUTS

P.A. Davies, Bruce Jamieson, B Reid

Open publisher page 13 citations

Abstract

Full signal control of traffic was introduced in 1978 at a 35 M diameter, three approach roundabout near the centre of Nottingham. This paper describes the development of the control method giving formulae used to determine cycle times, green times and junction capacities. Details are given of the sequence of traffic movements which allows at least one traffic stream to be entering the roundabout at all times within the cycle. Green periods for each entry slightly overlap allowing simultaneous entry for two streams over short times. Results of before-and-after surveys indicate that the entry capacity was increased by 10 to 40 percent according to the time of day, and that the flow could be significantly increased by junction control if it were accompanied by physical changes in layout. Other benefits include reduced delays and better overall control of the junction using urban traffic control systems.

About this research paper

What this paper is about

Full signal control of traffic was introduced in 1978 at a 35 M diameter, three approach roundabout near the centre of Nottingham. This paper describes the development of the control method giving formulae used to determine cycle times, green times and junction capacities. Details are given of the sequence of traffic movements which allows at least one traffic stream to be entering the roundabout at all times within the cycle. Green periods for each entry slightly overlap allowing simultaneous entry for two streams over short times. Results of before-and-after surveys indicate that the entry capacity was increased by 10 to 40 percent according to the time of day, and that the flow could be significantly increased by junction control if it were accompanied by physical changes in layout. Other benefits include reduced delays and better overall control of the junction using urban traffic control systems.

Why it matters

OpenAlex reports 13 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Full signal control of traffic was introduced in 1978 at a 35 M diameter, three approach roundabout near the centre of Nottingham. This paper describes the development of the control method giving formulae used to determine cycle times, green times and junction capacities. Details are given of the sequence of traffic movements which allows at least one traffic stream to be entering the roundabout at all times within the cycle. Green periods for each entry slightly overlap allowing simultaneous entry for two streams over short times. Results of before-and-after surveys indicate that the entry capacity was increased by 10 to 40 percent according to the time of day, and that the flow could be significantly increased by junction control if it were accompanied by physical changes in layout. Other benefits include reduced delays and better overall control of the junction using urban traffic control systems.

Key concepts: Roundabout, Traffic flow (computer networking), SIGNAL (programming language), Traffic signal, Control (management), Transport engineering, Computer science, Simulation