Field Performance of Epoxy-Coated Reinforcing Steel in Virginia Bridge Decks

Wioleta A. Pyc, Richard E. Weyers, R M Weyers, David W Mokarem, Jerzy Żemajtis, Michael M Sprinkel, John G. Dillard

Open full text 43 citations

Abstract

In this study, the corrosion protection performance of epoxy-coated reinforcing steel (ECR) was evaluated using approximately 250 concrete cores from 18 bridge decks in Virginia. The decks were 2 to 20 years old at the time of the investigation. The deck field inspections included a crack survey and cover depth determination in the right traffic lane. A maximum of 12 cores with the top reinforcement randomly located in the lowest 12th percentile cover depth were taken from each bridge deck. Because of the safety concerns associated with taking cores from the lower steel mat, and to minimize damage to the bridge, a maximum of only 3 cores were taken through the truss bars. The laboratory evaluation of the concrete cores included a visual examination and a determination of the carbonation depth, moisture content, absorption, percent saturation, and chloride content at a 13-mm depth. The rapid chloride permeability test was also performed for the surface and base concrete on samples obtained from the cores taken through the truss bars to determine chloride permeability. The ECR inspection consisted of a visual examination, a damage evaluation, and a determination of coating thickness and adhesion. The condition of the steel underneath the epoxy coating was also evaluated. Adhesion loss of the epoxy coating to the steel surface was detected in all but one deck that was 4 years old and older. The epoxy coatings were debonding from the reinforcing bars. Whereas a bonded coating can be expected to protect the steel, a debonded coating allows chlorides, moisture, and oxygen to reach the steel and initiate a rapid corrosion mechanism. Reinforcing bars in various stages of adhesion loss showed visible signs of a corrosion process underneath the coating, suggesting that ECR will provide little or no additional service life for concrete bridge decks in comparison to bare steel. Other systems that will provide longer protection against chloride-induced corrosion of the reinforcing steel with a higher degree of reliability should be considered.

Open-access reader

About this research paper

What this paper is about

In this study, the corrosion protection performance of epoxy-coated reinforcing steel (ECR) was evaluated using approximately 250 concrete cores from 18 bridge decks in Virginia. The decks were 2 to 20 years old at the time of the investigation. The deck field inspections included a crack survey and cover depth determination in the right traffic lane. A maximum of 12 cores with the top reinforcement randomly located in the lowest 12th percentile cover depth were taken from each bridge deck. Because of the safety concerns associated with taking cores from the lower steel mat, and to minimize damage to the bridge, a maximum of only 3 cores were taken through the truss bars. The laboratory evaluation of the concrete cores included a visual examination and a determination of the carbonation depth, moisture content, absorption, percent saturation, and chloride content at a 13-mm depth. The rapid chloride permeability test was also performed for the surface and base concrete on samples obtained from the cores taken through the truss bars to determine chloride permeability. The ECR inspection consisted of a visual examination, a damage evaluation, and a determination of coating thickness and adhesion. The condition of the steel underneath the epoxy coating was also evaluated. Adhesion loss of the epoxy coating to the steel surface was detected in all but one deck that was 4 years old and older. The epoxy coatings were debonding from the reinforcing bars. Whereas a bonded coating can be expected to protect the steel, a debonded coating allows chlorides, moisture, and oxygen to reach the steel and initiate a rapid corrosion mechanism. Reinforcing bars in various stages of adhesion loss showed visible signs of a corrosion process underneath the coating, suggesting that ECR will provide little or no additional service life for concrete bridge decks in comparison to bare steel. Other systems that will provide longer protection against chloride-induced corrosion of the reinforcing steel with a higher degree of reliability should be considered.

Why it matters

OpenAlex reports 43 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

In this study, the corrosion protection performance of epoxy-coated reinforcing steel (ECR) was evaluated using approximately 250 concrete cores from 18 bridge decks in Virginia. The decks were 2 to 20 years old at the time of the investigation. The deck field inspections included a crack survey and cover depth determination in the right traffic lane. A maximum of 12 cores with the top reinforcement randomly located in the lowest 12th percentile cover depth were taken from each bridge deck. Because of the safety concerns associated with taking cores from the lower steel mat, and to minimize damage to the bridge, a maximum of only 3 cores were taken through the truss bars. The laboratory evaluation of the concrete cores included a visual examination and a determination of the carbonation depth, moisture content, absorption, percent saturation, and chloride content at a 13-mm depth. The rapid chloride permeability test was also performed for the surface and base concrete on samples obtained from the cores taken through the truss bars to determine chloride permeability. The ECR inspection consisted of a visual examination, a damage evaluation, and a determination of coating thickness and adhesion. The condition of the steel underneath the epoxy coating was also evaluated. Adhesion loss of the epoxy coating to the steel surface was detected in all but one deck that was 4 years old and older. The epoxy coatings were debonding from the reinforcing bars. Whereas a bonded coating can be expected to protect the steel, a debonded coating allows chlorides, moisture, and oxygen to reach the steel and initiate a rapid corrosion mechanism. Reinforcing bars in various stages of adhesion loss showed visible signs of a corrosion process underneath the coating, suggesting that ECR will provide little or no additional service life for concrete bridge decks in comparison to bare steel. Other systems that will provide longer protection against chloride-induced corrosion of the reinforcing steel with a higher degree of reliability should be considered.

Key concepts: Epoxy, Materials science, Concrete cover, Coating, Composite material, Deck, Chloride, Carbonation

Related papers

Back to paper searchBrowse research topicsOriginal source
Field Performance of Epoxy-Coated Reinforcing Steel in Virginia Bridge Decks — Research Paper | ScholarLens