Corrosion protection service life of epoxy-coated reinforcing steel in Virginia bridge decks.

Michael C. Brown

Open full text 33 citations

Abstract

The corrosion protection service life extension provided by epoxy-coated reinforcement (ECR) was determined by comparing ECR and bare bar from 10 bridge decks built between 1981 and 1995. The objective was to determine the corrosion protection service life time extension provided by ECR field specimens with various degrees of coating adhesion: disbonded, partially disbonded, and wholly bonded coatings. The size and length distributions of cracks in Virginia bridge decks were investigated to assess the frequency and severity of cracks. Correlation of cracks with chloride penetration was used to characterize the influence of cracking on deck deterioration. Cracks influence the rate of chloride penetration, but the frequency and width distributions of cracks indicate that cracks are not likely to shorten the overall service life of most bridge decks in Virginia. Altogether, 141 drilled cores, 102 mm (4 inches) in diameter, were employed in this study. For each of the decks built with ECR, 10 to 12 cores were drilled through a top reinforcing bar adjacent to the previous study core locations. In addition, approximately 3 cores were drilled through a top reinforcing bar at a surface crack location. Laboratory testing involved nondestructive monitoring using advanced electrochemical techniques to periodically assess the corrosion state of the steel bars during cyclic exposure to chloride-rich solution over 22 months of treatment. Time of corrosion initiation and time of cracking (where applicable), as well as chloride content of the concrete before and after treatment, were used in the analysis. Less than 25 percent of all Virginia bridge decks built under specifications in place since 1981 is projected to corrode sufficiently to require rehabilitation within 100 years, regardless of bar type. The corrosion service life extension attributable to ECR in bridge decks was found to be approximately 5 years beyond that of bare steel.

Open-access reader

About this research paper

What this paper is about

The corrosion protection service life extension provided by epoxy-coated reinforcement (ECR) was determined by comparing ECR and bare bar from 10 bridge decks built between 1981 and 1995. The objective was to determine the corrosion protection service life time extension provided by ECR field specimens with various degrees of coating adhesion: disbonded, partially disbonded, and wholly bonded coatings. The size and length distributions of cracks in Virginia bridge decks were investigated to assess the frequency and severity of cracks. Correlation of cracks with chloride penetration was used to characterize the influence of cracking on deck deterioration. Cracks influence the rate of chloride penetration, but the frequency and width distributions of cracks indicate that cracks are not likely to shorten the overall service life of most bridge decks in Virginia. Altogether, 141 drilled cores, 102 mm (4 inches) in diameter, were employed in this study. For each of the decks built with ECR, 10 to 12 cores were drilled through a top reinforcing bar adjacent to the previous study core locations. In addition, approximately 3 cores were drilled through a top reinforcing bar at a surface crack location. Laboratory testing involved nondestructive monitoring using advanced electrochemical techniques to periodically assess the corrosion state of the steel bars during cyclic exposure to chloride-rich solution over 22 months of treatment. Time of corrosion initiation and time of cracking (where applicable), as well as chloride content of the concrete before and after treatment, were used in the analysis. Less than 25 percent of all Virginia bridge decks built under specifications in place since 1981 is projected to corrode sufficiently to require rehabilitation within 100 years, regardless of bar type. The corrosion service life extension attributable to ECR in bridge decks was found to be approximately 5 years beyond that of bare steel.

Why it matters

OpenAlex reports 33 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

The corrosion protection service life extension provided by epoxy-coated reinforcement (ECR) was determined by comparing ECR and bare bar from 10 bridge decks built between 1981 and 1995. The objective was to determine the corrosion protection service life time extension provided by ECR field specimens with various degrees of coating adhesion: disbonded, partially disbonded, and wholly bonded coatings. The size and length distributions of cracks in Virginia bridge decks were investigated to assess the frequency and severity of cracks. Correlation of cracks with chloride penetration was used to characterize the influence of cracking on deck deterioration. Cracks influence the rate of chloride penetration, but the frequency and width distributions of cracks indicate that cracks are not likely to shorten the overall service life of most bridge decks in Virginia. Altogether, 141 drilled cores, 102 mm (4 inches) in diameter, were employed in this study. For each of the decks built with ECR, 10 to 12 cores were drilled through a top reinforcing bar adjacent to the previous study core locations. In addition, approximately 3 cores were drilled through a top reinforcing bar at a surface crack location. Laboratory testing involved nondestructive monitoring using advanced electrochemical techniques to periodically assess the corrosion state of the steel bars during cyclic exposure to chloride-rich solution over 22 months of treatment. Time of corrosion initiation and time of cracking (where applicable), as well as chloride content of the concrete before and after treatment, were used in the analysis. Less than 25 percent of all Virginia bridge decks built under specifications in place since 1981 is projected to corrode sufficiently to require rehabilitation within 100 years, regardless of bar type. The corrosion service life extension attributable to ECR in bridge decks was found to be approximately 5 years beyond that of bare steel.

Key concepts: Service life, Corrosion, Materials science, Epoxy, Cracking, Chloride, Coating, Composite material

Related papers

Back to paper searchBrowse research topicsOriginal source
Corrosion protection service life of epoxy-coated reinforcing steel in Virginia bridge decks. — Research Paper | ScholarLens