Construction Project Evaluation Using CPM-Crashing, CPM-PERT and CCPM for Minimize Project Delays
Andiyan Andiyan, Raditya Mandala Putra, Glisina Dwinoor Rembulan, Hendy Tannady
Abstract
Open-access reader
Andiyan Andiyan, Raditya Mandala Putra, Glisina Dwinoor Rembulan, Hendy Tannady
Abstract
Open-access reader
Abstract This research conducted in one construction company in Indonesia, the company was facing several problems, many projects that already ended have delays. Overdue payment one of the projects can reach Rp 252.544.148.-. For calculating late payment that the company can save researcher using Critical Path Method (CPM)-Crashing. CPM-Crashing method can accelerate project duration by increase resource budget, so company doesn’t need to pay overdue payment. The result of CPM-Crashing is company can save Rp. 227.584.147.-late payment. To anticipate project delay proper planning is required. One of project planning method is project scheduling. Great loss because of the overdue amount, the company must evaluate their project schedule. The Researcher using CPM-Project Evaluation Review Technic (PERT) and Critical Chain Project Management (CCPM) both methods can give new project schedule. CPM-PERT can give probability project finish and CCPM can give new project schedule. The result of this research is probability project is not delay is very low that is only 55% project can finish on time, the company must try CCPM schedule.
OpenAlex reports 35 citations for this work. Citation counts describe recorded attention and do not establish research quality.
A contribution statement is not available in the OpenAlex record.
Method details are not available in the OpenAlex metadata.
Findings are not separately available in the OpenAlex metadata.
Limitations are not available in the OpenAlex metadata.
Application details are not available in the OpenAlex metadata.
Abstract This research conducted in one construction company in Indonesia, the company was facing several problems, many projects that already ended have delays. Overdue payment one of the projects can reach Rp 252.544.148.-. For calculating late payment that the company can save researcher using Critical Path Method (CPM)-Crashing. CPM-Crashing method can accelerate project duration by increase resource budget, so company doesn’t need to pay overdue payment. The result of CPM-Crashing is company can save Rp. 227.584.147.-late payment. To anticipate project delay proper planning is required. One of project planning method is project scheduling. Great loss because of the overdue amount, the company must evaluate their project schedule. The Researcher using CPM-Project Evaluation Review Technic (PERT) and Critical Chain Project Management (CCPM) both methods can give new project schedule. CPM-PERT can give probability project finish and CCPM can give new project schedule. The result of this research is probability project is not delay is very low that is only 55% project can finish on time, the company must try CCPM schedule.
Key concepts: Critical path method, Schedule, Project management, Project planning, Payment, Computer science, Duration (music), Operations research