A remedy measure for large cavities of an existing tunnel

Kwang-Ho You, Kwang-Joon Park, Chul-Soon Lim

Open publisher page 0 citations

Abstract

During enlarging an existing tunnel under operation, unexpected excessive overbreaks and large cavities around the tunnel were found. It was an issue that they might influence the stability the new tunnel. The overbreaks and cavities are assumed that they were attributed to excessive blasting under the condition of insufficient ground investigation. To enlarge the existing tunnel safely, therefore, a remedy measure for the overbreaks and cavities is suggested.

About this research paper

What this paper is about

During enlarging an existing tunnel under operation, unexpected excessive overbreaks and large cavities around the tunnel were found. It was an issue that they might influence the stability the new tunnel. The overbreaks and cavities are assumed that they were attributed to excessive blasting under the condition of insufficient ground investigation. To enlarge the existing tunnel safely, therefore, a remedy measure for the overbreaks and cavities is suggested.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

During enlarging an existing tunnel under operation, unexpected excessive overbreaks and large cavities around the tunnel were found. It was an issue that they might influence the stability the new tunnel. The overbreaks and cavities are assumed that they were attributed to excessive blasting under the condition of insufficient ground investigation. To enlarge the existing tunnel safely, therefore, a remedy measure for the overbreaks and cavities is suggested.

Key concepts: Measure (data warehouse), Rock blasting, Forensic engineering, Engineering, Geotechnical engineering, Computer science, Database

Related papers

Back to paper searchBrowse research topicsOriginal source
A remedy measure for large cavities of an existing tunnel — Research Paper | ScholarLens