1992Civil engineeringRequires access

Rehabbing the Rails

Stewart D. Winn

Open publisher page 0 citations

Abstract

In 1984, during a routine bridge inspection, a worker detected deterioration under the south abutment of a bridge that carried the main line of Philadelphia's commuter railroad. The bridge was about to fail. The Southeastern Pennsylvania Transportation Authority (SEPTA) shut down the railroad for four weeks to replace two of the bridge spans with earth fill. At the same time, SEPTA surveyed the entire line (which runs from Philadelphia's Center City to the suburbs) and found that 25 bridges were reaching the end of their service life. The line's former owners, now bankrupt, had deferred years of heavy maintenance. Extensive renovation or replacement of all bridges, track and equipment was necessary. After several years of planning, construction on Railworks, a $354 million overhaul of the line, began last spring. SEPTA operates all transit service in the Philadelphia area, providing bus, light rail and heavy commuter rail service using the facilities of several formerly privately owned railroads.

About this research paper

What this paper is about

In 1984, during a routine bridge inspection, a worker detected deterioration under the south abutment of a bridge that carried the main line of Philadelphia's commuter railroad. The bridge was about to fail. The Southeastern Pennsylvania Transportation Authority (SEPTA) shut down the railroad for four weeks to replace two of the bridge spans with earth fill. At the same time, SEPTA surveyed the entire line (which runs from Philadelphia's Center City to the suburbs) and found that 25 bridges were reaching the end of their service life. The line's former owners, now bankrupt, had deferred years of heavy maintenance. Extensive renovation or replacement of all bridges, track and equipment was necessary. After several years of planning, construction on Railworks, a $354 million overhaul of the line, began last spring. SEPTA operates all transit service in the Philadelphia area, providing bus, light rail and heavy commuter rail service using the facilities of several formerly privately owned railroads.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

In 1984, during a routine bridge inspection, a worker detected deterioration under the south abutment of a bridge that carried the main line of Philadelphia's commuter railroad. The bridge was about to fail. The Southeastern Pennsylvania Transportation Authority (SEPTA) shut down the railroad for four weeks to replace two of the bridge spans with earth fill. At the same time, SEPTA surveyed the entire line (which runs from Philadelphia's Center City to the suburbs) and found that 25 bridges were reaching the end of their service life. The line's former owners, now bankrupt, had deferred years of heavy maintenance. Extensive renovation or replacement of all bridges, track and equipment was necessary. After several years of planning, construction on Railworks, a $354 million overhaul of the line, began last spring. SEPTA operates all transit service in the Philadelphia area, providing bus, light rail and heavy commuter rail service using the facilities of several formerly privately owned railroads.

Key concepts: Bridge (graph theory), Engineering, Shut down, Service (business), Track (disk drive), Transport engineering, Light rail, Forensic engineering

Related papers

Back to paper searchBrowse research topicsOriginal source
Rehabbing the Rails — Research Paper | ScholarLens