Research on Improving Schedule Forecasting Method for Delayed Defense Research & Development Project

Jungho Cho, Jaesung Lim

Open full text 0 citations

Abstract

Since Dr. Lipke announces earned schedule management(ESM) in 2002, it has been used in project management to make up for the insufficient schedule management function of earned value management technique.However, it is difficult to accurately forecast the schedule of delayed defense research and development(R&D) projects with the ESM technique.Therefore, this paper proposes a new schedule forecasting method considering the progress of delayed work in ESM technique.This concept can also be adopted to the traditional project progress management (PPM) technique.We verify the effectiveness of the proposed concept through several defense R&D projects and prove that it is possible to supplement the schedule forecasting of the ESM and PPM technique.

Open-access reader

About this research paper

What this paper is about

Since Dr. Lipke announces earned schedule management(ESM) in 2002, it has been used in project management to make up for the insufficient schedule management function of earned value management technique.However, it is difficult to accurately forecast the schedule of delayed defense research and development(R&D) projects with the ESM technique.Therefore, this paper proposes a new schedule forecasting method considering the progress of delayed work in ESM technique.This concept can also be adopted to the traditional project progress management (PPM) technique.We verify the effectiveness of the proposed concept through several defense R&D projects and prove that it is possible to supplement the schedule forecasting of the ESM and PPM technique.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Since Dr. Lipke announces earned schedule management(ESM) in 2002, it has been used in project management to make up for the insufficient schedule management function of earned value management technique.However, it is difficult to accurately forecast the schedule of delayed defense research and development(R&D) projects with the ESM technique.Therefore, this paper proposes a new schedule forecasting method considering the progress of delayed work in ESM technique.This concept can also be adopted to the traditional project progress management (PPM) technique.We verify the effectiveness of the proposed concept through several defense R&D projects and prove that it is possible to supplement the schedule forecasting of the ESM and PPM technique.

Key concepts: Schedule, Earned value management, Project management, Operations research, Computer science, Work schedule, Work (physics), Project planning