Schedule Risk Analysis by Different Phases of Construction Project Using CPM-PERT and Monte-Carlo Simulation
Andrie Pasca Hendradewa
Abstract
Open-access reader
Andrie Pasca Hendradewa
Abstract
Open-access reader
Abstract Construction project is an important activity along with the increasing need of infrastructure and residential building. Construction projects with different investment value and complexity level affect the completion duration of construction work. The higher the value or the more complex the building, the longer time required to accomplish the construction project. During the construction process, it is possible to find risks both from internal and external management which potentially cause project overdue that will lead to cost overruns. This study focused on assessing and managing schedule risk in three main phases of construction project, such as: feasibility study, design, and construction. A certain sample of residential building project was choosen as study case. In this study, mathematical approaches are used by performing CPM-PERT and Monte-Carlo simulation method. The results of this study can be used to help project managers to minimize potential risks by projecting simulation results and to assess if a project can be completed in timely manner according to given schedule.
OpenAlex reports 26 citations for this work. Citation counts describe recorded attention and do not establish research quality.
A contribution statement is not available in the OpenAlex record.
Method details are not available in the OpenAlex metadata.
Findings are not separately available in the OpenAlex metadata.
Limitations are not available in the OpenAlex metadata.
Application details are not available in the OpenAlex metadata.
Abstract Construction project is an important activity along with the increasing need of infrastructure and residential building. Construction projects with different investment value and complexity level affect the completion duration of construction work. The higher the value or the more complex the building, the longer time required to accomplish the construction project. During the construction process, it is possible to find risks both from internal and external management which potentially cause project overdue that will lead to cost overruns. This study focused on assessing and managing schedule risk in three main phases of construction project, such as: feasibility study, design, and construction. A certain sample of residential building project was choosen as study case. In this study, mathematical approaches are used by performing CPM-PERT and Monte-Carlo simulation method. The results of this study can be used to help project managers to minimize potential risks by projecting simulation results and to assess if a project can be completed in timely manner according to given schedule.
Key concepts: Schedule, Project management, Duration (music), Project planning, Monte Carlo method, Operations research, Construction management, Risk analysis (engineering)