DETERMINATION OF STANDARD TIME IN PACKAGING PROCESSING USING STOPWATCH TIME STUDY TO FIND OUTPUT STANDARD

Rio Prasetyo Lukodono, Siti Kholisotul Ulfa

Open full text 14 citations

Abstract

Time is one of the factors to assess a worker's performance in utilizing the available resources. Operator in his work requires efficient time to improve work productivity. One of factory in produce a shrimp feed in Surabaya has a large production level. In the production process, the packaging department in this company still uses human resources in their production process and the company define the standard of production without using standard time. This paper investigates the opportunity a logical analysis in determining the standard time in this company. The determination of the standard time in the packaging process requires comprehensive analysis. Objects observed are four operators in the packaging department that carried out the activities of filling bag the shrimp feed with 40 replication for each data. The work measurement was conducted by direct method using Stopwatch Time Study (STS) with snap-back method. The results of this study indicate the standard time value of the four lines packaging is not much different or almost the same. Sequentially the standard time workers line 1 to line 4 is 7.325 seconds, 7.240 seconds, 7.225 seconds, and 7.065 seconds. Allowance used for workers is 8%. However, the existing production rate of company is higher than the production rate of work measurement calculation. This is due to the difference of definition in employee allowance rate and performance rating.

Open-access reader

About this research paper

What this paper is about

Time is one of the factors to assess a worker's performance in utilizing the available resources. Operator in his work requires efficient time to improve work productivity. One of factory in produce a shrimp feed in Surabaya has a large production level. In the production process, the packaging department in this company still uses human resources in their production process and the company define the standard of production without using standard time. This paper investigates the opportunity a logical analysis in determining the standard time in this company. The determination of the standard time in the packaging process requires comprehensive analysis. Objects observed are four operators in the packaging department that carried out the activities of filling bag the shrimp feed with 40 replication for each data. The work measurement was conducted by direct method using Stopwatch Time Study (STS) with snap-back method. The results of this study indicate the standard time value of the four lines packaging is not much different or almost the same. Sequentially the standard time workers line 1 to line 4 is 7.325 seconds, 7.240 seconds, 7.225 seconds, and 7.065 seconds. Allowance used for workers is 8%. However, the existing production rate of company is higher than the production rate of work measurement calculation. This is due to the difference of definition in employee allowance rate and performance rating.

Why it matters

OpenAlex reports 14 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Time is one of the factors to assess a worker's performance in utilizing the available resources. Operator in his work requires efficient time to improve work productivity. One of factory in produce a shrimp feed in Surabaya has a large production level. In the production process, the packaging department in this company still uses human resources in their production process and the company define the standard of production without using standard time. This paper investigates the opportunity a logical analysis in determining the standard time in this company. The determination of the standard time in the packaging process requires comprehensive analysis. Objects observed are four operators in the packaging department that carried out the activities of filling bag the shrimp feed with 40 replication for each data. The work measurement was conducted by direct method using Stopwatch Time Study (STS) with snap-back method. The results of this study indicate the standard time value of the four lines packaging is not much different or almost the same. Sequentially the standard time workers line 1 to line 4 is 7.325 seconds, 7.240 seconds, 7.225 seconds, and 7.065 seconds. Allowance used for workers is 8%. However, the existing production rate of company is higher than the production rate of work measurement calculation. This is due to the difference of definition in employee allowance rate and performance rating.

Key concepts: Stopwatch, Standard time, Allowance (engineering), Production line, Production (economics), Work (physics), Factory (object-oriented programming), Process (computing)