Minimizing the Number of Tardy Jobs in the Single Machine Scheduling Problem under Bimodal Flexible and Periodic Availability Constraints

Ghasem Moslehi, Omolbanin Mashkani

Open full text 0 citations

Abstract

In single machine scheduling problems with availability constraints, machines are not available for one or more periods of time. In this paper, we consider a single machine scheduling problem with flexible and periodic availability constraints. In this problem, the maximum continuous working time for each machine increases in a stepwise manner with two different values allowed. Also, the duration of unavailability for each period depends on the maximum continuous working time of the machine in that same period, again with two different values allowed. The objective is to minimize the number of tardy jobs. In the first stage, the complexity of the problem is investigated and a binary integer programming model, a heuristic algorithm and a branch-and-bound algorithm are proposed in a second stage. Computational results of solving 1680 sample problems indicate that the branch-and-bound algorithm is capable of not only solving problems of up to 20 jobs but also of optimally solving 94.76% of the total number of problems. Based on numerical results obtained, a mean average error of 2% is obtained for the heuristic algorithm.

About this research paper

What this paper is about

In single machine scheduling problems with availability constraints, machines are not available for one or more periods of time. In this paper, we consider a single machine scheduling problem with flexible and periodic availability constraints. In this problem, the maximum continuous working time for each machine increases in a stepwise manner with two different values allowed. Also, the duration of unavailability for each period depends on the maximum continuous working time of the machine in that same period, again with two different values allowed. The objective is to minimize the number of tardy jobs. In the first stage, the complexity of the problem is investigated and a binary integer programming model, a heuristic algorithm and a branch-and-bound algorithm are proposed in a second stage. Computational results of solving 1680 sample problems indicate that the branch-and-bound algorithm is capable of not only solving problems of up to 20 jobs but also of optimally solving 94.76% of the total number of problems. Based on numerical results obtained, a mean average error of 2% is obtained for the heuristic algorithm.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

In single machine scheduling problems with availability constraints, machines are not available for one or more periods of time. In this paper, we consider a single machine scheduling problem with flexible and periodic availability constraints. In this problem, the maximum continuous working time for each machine increases in a stepwise manner with two different values allowed. Also, the duration of unavailability for each period depends on the maximum continuous working time of the machine in that same period, again with two different values allowed. The objective is to minimize the number of tardy jobs. In the first stage, the complexity of the problem is investigated and a binary integer programming model, a heuristic algorithm and a branch-and-bound algorithm are proposed in a second stage. Computational results of solving 1680 sample problems indicate that the branch-and-bound algorithm is capable of not only solving problems of up to 20 jobs but also of optimally solving 94.76% of the total number of problems. Based on numerical results obtained, a mean average error of 2% is obtained for the heuristic algorithm.

Key concepts: Scheduling (production processes), Computer science, Mathematical optimization, Due date, Single-machine scheduling, Operations management, Job shop scheduling, Operations research