2016•CERN Document Server (European Organization for Nuclear Research)Open access

Beam Commissioning of the HIE-ISOLDE Post-Accelerator

José A. Rodríguez, William Andreazza, J. Bibby, Niels Bidault, E. Bravin, J Broere, E. D. Cantero, R. Catherall, Vince Cobham, Michal Elias, Eleftherios Fadakis, P. Fernier, Matthew Fraser, F. Gerigk, K. Hanke, Yacine Kadi, Miguel Lozano Benito, Emanuele Matli, Sergey Sadovich, E. Siesling, Daniel Valuch, Walter Venturini Delsolaro, F. Wenander, Pei Zhang

Open full text 0 citations

Abstract

Phase 1a of the High Intensity and Energy ISOLDE (HIE-ISOLDE) project* was completed in 2015. The first cryomodule and two High Energy Beam Transfer lines (HEBT) were installed. In addition, many of the subsystems of the normal conducting part of the post-accelerator (REX) were renovated or refurbished. Following the hardware commissioning of the different system** and, in preparation for the start of the physics program, many tests and measurements were conducted as part of the beam commissioning program. The results of these tests and the plan for the next beam commissioning campaign are discussed in this paper.

Open-access reader

About this research paper

What this paper is about

Phase 1a of the High Intensity and Energy ISOLDE (HIE-ISOLDE) project* was completed in 2015. The first cryomodule and two High Energy Beam Transfer lines (HEBT) were installed. In addition, many of the subsystems of the normal conducting part of the post-accelerator (REX) were renovated or refurbished. Following the hardware commissioning of the different system** and, in preparation for the start of the physics program, many tests and measurements were conducted as part of the beam commissioning program. The results of these tests and the plan for the next beam commissioning campaign are discussed in this paper.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Phase 1a of the High Intensity and Energy ISOLDE (HIE-ISOLDE) project* was completed in 2015. The first cryomodule and two High Energy Beam Transfer lines (HEBT) were installed. In addition, many of the subsystems of the normal conducting part of the post-accelerator (REX) were renovated or refurbished. Following the hardware commissioning of the different system** and, in preparation for the start of the physics program, many tests and measurements were conducted as part of the beam commissioning program. The results of these tests and the plan for the next beam commissioning campaign are discussed in this paper.

Key concepts: Beam (structure), Physics, Optics