Monitoring of Movements above Large Shallow Jacked Tunnels

Charles Daugherty

Open publisher page 0 citations

Abstract

The construction of CA/T Contract C09A4 entails the jacking of three (reduced from four) tunnels beneath eight sets of Amtrak and MBTA commuter rail tracks at South Station in downtown Boston. The tunnels range up to 38 feet (11.5m) in height and 79 feet (24m) in width, and crowns are separated from the tracks by only 8 to 23 feet (2.4 to 7m) of manmade fill. The original design called for the tunneled ground to be extensively treated with a combination of dewatering, jet grouting, penetration grouting and soil nailing, but surface settlements could still have reached as much as 13.5 inches (34cm). There was need to monitor both subsurface movements and rail settlements to protect the tracks, so designers provided for 200 subsurface instruments of eight different types, upwards of 1200 optical survey points on tops of rails, 1200 railroad hubs for determining dynamic rail movements, and special software developed to quickly sort and report hundreds of rail elevation measurements made every day. Studied and rejected were a computerized hand propelled Portable Geometry Trolley for measuring static rail elevations and an extensive array of remote reading Electrolevels and Beams for determining both static and dynamic rail elevations. The post-bid deletion of one tunnel and replacement of design ground treatment with ground freezing forced construction managers to continually adjust the mix of instrument types, numbers, locations and installation procedures to stay abreast of developments.

About this research paper

What this paper is about

The construction of CA/T Contract C09A4 entails the jacking of three (reduced from four) tunnels beneath eight sets of Amtrak and MBTA commuter rail tracks at South Station in downtown Boston. The tunnels range up to 38 feet (11.5m) in height and 79 feet (24m) in width, and crowns are separated from the tracks by only 8 to 23 feet (2.4 to 7m) of manmade fill. The original design called for the tunneled ground to be extensively treated with a combination of dewatering, jet grouting, penetration grouting and soil nailing, but surface settlements could still have reached as much as 13.5 inches (34cm). There was need to monitor both subsurface movements and rail settlements to protect the tracks, so designers provided for 200 subsurface instruments of eight different types, upwards of 1200 optical survey points on tops of rails, 1200 railroad hubs for determining dynamic rail movements, and special software developed to quickly sort and report hundreds of rail elevation measurements made every day. Studied and rejected were a computerized hand propelled Portable Geometry Trolley for measuring static rail elevations and an extensive array of remote reading Electrolevels and Beams for determining both static and dynamic rail elevations. The post-bid deletion of one tunnel and replacement of design ground treatment with ground freezing forced construction managers to continually adjust the mix of instrument types, numbers, locations and installation procedures to stay abreast of developments.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

The construction of CA/T Contract C09A4 entails the jacking of three (reduced from four) tunnels beneath eight sets of Amtrak and MBTA commuter rail tracks at South Station in downtown Boston. The tunnels range up to 38 feet (11.5m) in height and 79 feet (24m) in width, and crowns are separated from the tracks by only 8 to 23 feet (2.4 to 7m) of manmade fill. The original design called for the tunneled ground to be extensively treated with a combination of dewatering, jet grouting, penetration grouting and soil nailing, but surface settlements could still have reached as much as 13.5 inches (34cm). There was need to monitor both subsurface movements and rail settlements to protect the tracks, so designers provided for 200 subsurface instruments of eight different types, upwards of 1200 optical survey points on tops of rails, 1200 railroad hubs for determining dynamic rail movements, and special software developed to quickly sort and report hundreds of rail elevation measurements made every day. Studied and rejected were a computerized hand propelled Portable Geometry Trolley for measuring static rail elevations and an extensive array of remote reading Electrolevels and Beams for determining both static and dynamic rail elevations. The post-bid deletion of one tunnel and replacement of design ground treatment with ground freezing forced construction managers to continually adjust the mix of instrument types, numbers, locations and installation procedures to stay abreast of developments.

Key concepts: Jacking, Engineering, Elevation (ballistics), Geology, Geotechnical engineering, Marine engineering, Structural engineering, Art history

Related papers

Back to paper searchBrowse research topicsOriginal source
Monitoring of Movements above Large Shallow Jacked Tunnels — Research Paper | ScholarLens