Causes analysis and treatment of extra-long Yunzhongshan tunnel collapse

Yong Liu

Open publisher page 0 citations

Abstract

This paper introduces the whole process of arch top instability and collapse at left railway line LK43+642~LK43+660 of extra-long Yunzhongshan tunnel,the paper analyzes the collapse causes from three aspects of geological causes,leakages and erosion,and construction factors and inaccurate preliminary geology prediction and so on.Combining with specific engineering conditions,it puts forward safe and reliable collapse processing measures.In the process of treatment,it neither influences the security of existing railway line nor fail to complete the construction at collapse section.

About this research paper

What this paper is about

This paper introduces the whole process of arch top instability and collapse at left railway line LK43+642~LK43+660 of extra-long Yunzhongshan tunnel,the paper analyzes the collapse causes from three aspects of geological causes,leakages and erosion,and construction factors and inaccurate preliminary geology prediction and so on.Combining with specific engineering conditions,it puts forward safe and reliable collapse processing measures.In the process of treatment,it neither influences the security of existing railway line nor fail to complete the construction at collapse section.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

This paper introduces the whole process of arch top instability and collapse at left railway line LK43+642~LK43+660 of extra-long Yunzhongshan tunnel,the paper analyzes the collapse causes from three aspects of geological causes,leakages and erosion,and construction factors and inaccurate preliminary geology prediction and so on.Combining with specific engineering conditions,it puts forward safe and reliable collapse processing measures.In the process of treatment,it neither influences the security of existing railway line nor fail to complete the construction at collapse section.

Key concepts: Arch, Forensic engineering, Engineering, Process (computing), Section (typography), Geology, Computer science, Civil engineering

Related papers

Back to paper searchBrowse research topicsOriginal source
Causes analysis and treatment of extra-long Yunzhongshan tunnel collapse — Research Paper | ScholarLens