Abstract

Zhentouba I Hydropower Station locates at a narrow valley on Dadu River with a larger flood discharge. Through technical and economic analyses and considering surrounding social environment factors, the diversion of project is chosen as an open channel diversion type with three stages. For achieving the target of putting the first unit into operation in October 2014,the diversion process planning and the layout and structure design of diversion buildings are optimized and adjusted during construction according to the changes of actual construction conditions. Due to these measures, the pre-determined target is basically achieved on time and the diversion buildings operate well during construction. The adjustment and optimization of diversion design is successful.

About this research paper

What this paper is about

Zhentouba I Hydropower Station locates at a narrow valley on Dadu River with a larger flood discharge. Through technical and economic analyses and considering surrounding social environment factors, the diversion of project is chosen as an open channel diversion type with three stages. For achieving the target of putting the first unit into operation in October 2014,the diversion process planning and the layout and structure design of diversion buildings are optimized and adjusted during construction according to the changes of actual construction conditions. Due to these measures, the pre-determined target is basically achieved on time and the diversion buildings operate well during construction. The adjustment and optimization of diversion design is successful.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Zhentouba I Hydropower Station locates at a narrow valley on Dadu River with a larger flood discharge. Through technical and economic analyses and considering surrounding social environment factors, the diversion of project is chosen as an open channel diversion type with three stages. For achieving the target of putting the first unit into operation in October 2014,the diversion process planning and the layout and structure design of diversion buildings are optimized and adjusted during construction according to the changes of actual construction conditions. Due to these measures, the pre-determined target is basically achieved on time and the diversion buildings operate well during construction. The adjustment and optimization of diversion design is successful.

Key concepts: Hydropower, Water diversion, Civil engineering, Flood myth, Unit (ring theory), Process (computing), Engineering, Environmental science

Related papers

Back to paper searchBrowse research topicsOriginal source
Diversion Design and Optimization in the Staged Construction of Zhentouba I Hydropower Station — Research Paper | ScholarLens