Study on Construction Technology of A 3-arch Tunnel on Xiongmaohuandao Link Line in Beijing Metro

Yang Shiwu

Open publisher page 0 citations

Abstract

The 3-arch tunnel on Xiongmaohuandao link line of Line 10 in Beijing Metro passes through the ground consisting of silty clay and medium-coarse sand, which is constructed by means of the CRD method. The central drift of the tunnel is excavated first, which is followed by the excavation of the side drifts. The conversion of the force-bearing of the tunnel during construction is very complex and the settlement occurring in different excavation steps has great impact on the settlement of ground. By means of adopting proper construction methods and modifying the reinforcement parameters on the basis of the monitoring data, the safety and stability of the tunnel are guaranteed and the difficult problems in the construction of shallow tunnels with complex force-bearing structures are solved.

About this research paper

What this paper is about

The 3-arch tunnel on Xiongmaohuandao link line of Line 10 in Beijing Metro passes through the ground consisting of silty clay and medium-coarse sand, which is constructed by means of the CRD method. The central drift of the tunnel is excavated first, which is followed by the excavation of the side drifts. The conversion of the force-bearing of the tunnel during construction is very complex and the settlement occurring in different excavation steps has great impact on the settlement of ground. By means of adopting proper construction methods and modifying the reinforcement parameters on the basis of the monitoring data, the safety and stability of the tunnel are guaranteed and the difficult problems in the construction of shallow tunnels with complex force-bearing structures are solved.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

The 3-arch tunnel on Xiongmaohuandao link line of Line 10 in Beijing Metro passes through the ground consisting of silty clay and medium-coarse sand, which is constructed by means of the CRD method. The central drift of the tunnel is excavated first, which is followed by the excavation of the side drifts. The conversion of the force-bearing of the tunnel during construction is very complex and the settlement occurring in different excavation steps has great impact on the settlement of ground. By means of adopting proper construction methods and modifying the reinforcement parameters on the basis of the monitoring data, the safety and stability of the tunnel are guaranteed and the difficult problems in the construction of shallow tunnels with complex force-bearing structures are solved.

Key concepts: Excavation, Arch, Settlement (finance), Beijing, Engineering, Geotechnical engineering, Bearing (navigation), Main bearing

Related papers

Back to paper searchBrowse research topicsOriginal source
Study on Construction Technology of A 3-arch Tunnel on Xiongmaohuandao Link Line in Beijing Metro — Research Paper | ScholarLens