2007•Qiaoliang jiansheRequires access

Simulation Analysis of Construction Control of Pylon of a Single Pylon Cable-Stayed Bridge Without Backstays

Xin Wei

Open publisher page 0 citations

Abstract

The concrete for pylon of the single pylon cablestayed bridge without backstays on the Light Rail Transit in Changchun City was cast in situ on scaffolding.Since it was required that the settlement value of the arm section of the pylon should not be greater than 2 cm,the construction technique of pre-applying the jack-up force to the arm section of the pylon was applied in construction.In this paper,the simulation analysis of various construction stages of the pylon is made.The analysis shows that the construction technique of applying the jack-up force can meet the requirements for stress and deformation in the construction of the pylon.The operation with the construction technique is simple,reliable and can also ensure the construction time schedule.

About this research paper

What this paper is about

The concrete for pylon of the single pylon cablestayed bridge without backstays on the Light Rail Transit in Changchun City was cast in situ on scaffolding.Since it was required that the settlement value of the arm section of the pylon should not be greater than 2 cm,the construction technique of pre-applying the jack-up force to the arm section of the pylon was applied in construction.In this paper,the simulation analysis of various construction stages of the pylon is made.The analysis shows that the construction technique of applying the jack-up force can meet the requirements for stress and deformation in the construction of the pylon.The operation with the construction technique is simple,reliable and can also ensure the construction time schedule.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

The concrete for pylon of the single pylon cablestayed bridge without backstays on the Light Rail Transit in Changchun City was cast in situ on scaffolding.Since it was required that the settlement value of the arm section of the pylon should not be greater than 2 cm,the construction technique of pre-applying the jack-up force to the arm section of the pylon was applied in construction.In this paper,the simulation analysis of various construction stages of the pylon is made.The analysis shows that the construction technique of applying the jack-up force can meet the requirements for stress and deformation in the construction of the pylon.The operation with the construction technique is simple,reliable and can also ensure the construction time schedule.

Key concepts: Pylon, Engineering, Bridge (graph theory), Structural engineering, Settlement (finance), Computer science, Medicine, Internal medicine