Simulation Analysis of Cable-stayed Bridge Pylon Construction Process

LI Hou-min

Open publisher page 0 citations

Abstract

With Shennongxi cable-stayed bridge pylon as the research object, the article used the finite element analysis software Midas/Civil to establish the pylon's spatial model, conducted the simulation analysis on two construction plans of pylon with temporary support and without temporary support, and the results showed that : the temporary support steel pipe in the pylon leaning-tower column construction process can reduce the stress of leaning-tower column and can optimize the stress state of pylon.

About this research paper

What this paper is about

With Shennongxi cable-stayed bridge pylon as the research object, the article used the finite element analysis software Midas/Civil to establish the pylon's spatial model, conducted the simulation analysis on two construction plans of pylon with temporary support and without temporary support, and the results showed that : the temporary support steel pipe in the pylon leaning-tower column construction process can reduce the stress of leaning-tower column and can optimize the stress state of pylon.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

With Shennongxi cable-stayed bridge pylon as the research object, the article used the finite element analysis software Midas/Civil to establish the pylon's spatial model, conducted the simulation analysis on two construction plans of pylon with temporary support and without temporary support, and the results showed that : the temporary support steel pipe in the pylon leaning-tower column construction process can reduce the stress of leaning-tower column and can optimize the stress state of pylon.

Key concepts: Pylon, Structural engineering, Bridge (graph theory), Tower, Engineering, Finite element method, Column (typography), Stress (linguistics)

Related papers

Back to paper searchBrowse research topicsOriginal source
Simulation Analysis of Cable-stayed Bridge Pylon Construction Process — Research Paper | ScholarLens