The Measures and Construction Methods about the Open Full-face Tunnel Boring Machine Going through the Bad Geology Area
Gao Xiao-dong
Abstract
Gao Xiao-dong
Abstract
Research purposes: Two sets of TB880E TBM manufactured by German Wirth Corporation were introduced in 1997 by the Railway Ministry. These machines’ structures and technical data were designed according to Qinling Super Long Tunnel of Xi’an-Ankang Railway, which were applicable to excavating construction of hard rock tunnel, that was, Open Hard Rock Tunnel Boring Machine (TBM). It is still a difficult problem suffering the world to excavate through the soft surrounding rock. Research methods:This paper researched the preventive measures and construction methods on TBM construction accidents in terms of Taohuapu No.1 tunnel construction practice of Xi’an-Nanjing Railway. Research conclusions:This paper proposed a 20-Chinese-word principle, “Advance prediction, lining construction, data adjustment, proper promotion, and disturbance reduction”. How to deal with landslide was also described in the paper, in conclusion, “Anchor spraying in time, steel-rack sealing, steel pipe lap-welding, otter board combining, slump blocking, and dense refilling”. TBM excavating through the section of unfavorable geological condition smoothly and safely was validated in Taohuapu No.1 tunnel construction
A significance statement is not available in the OpenAlex record.
A contribution statement is not available in the OpenAlex record.
Method details are not available in the OpenAlex metadata.
Findings are not separately available in the OpenAlex metadata.
Limitations are not available in the OpenAlex metadata.
Application details are not available in the OpenAlex metadata.
Research purposes: Two sets of TB880E TBM manufactured by German Wirth Corporation were introduced in 1997 by the Railway Ministry. These machines’ structures and technical data were designed according to Qinling Super Long Tunnel of Xi’an-Ankang Railway, which were applicable to excavating construction of hard rock tunnel, that was, Open Hard Rock Tunnel Boring Machine (TBM). It is still a difficult problem suffering the world to excavate through the soft surrounding rock. Research methods:This paper researched the preventive measures and construction methods on TBM construction accidents in terms of Taohuapu No.1 tunnel construction practice of Xi’an-Nanjing Railway. Research conclusions:This paper proposed a 20-Chinese-word principle, “Advance prediction, lining construction, data adjustment, proper promotion, and disturbance reduction”. How to deal with landslide was also described in the paper, in conclusion, “Anchor spraying in time, steel-rack sealing, steel pipe lap-welding, otter board combining, slump blocking, and dense refilling”. TBM excavating through the section of unfavorable geological condition smoothly and safely was validated in Taohuapu No.1 tunnel construction
Key concepts: Engineering, Tunnel construction, Slump, Mining engineering, Tunnel boring machine, Civil engineering, Three gorges, Christian ministry