ANALYSIS OF INFLUENCE ON POST-CONSTRUCTION SETTLEMENT OF EXISTING EMBANKMENT BY FILLING NEWLY WIDENED SUBGRADE

Ming Yuan

Open publisher page 0 citations

Abstract

Based on the crack change and settlement monitoring result of one embankment, this paper gives a conclusion that crack occurring to existing embankment is caused by unbalanced settlements between old embankment and new embankment owing to the outside force during filling newly widened subgrade in combination with theoretic analysis, proposes the suggestion that two aspects, namely materials and depth of subgrade treatment and reinforcing embankment body, should be considered for treatment of connection between new subgrade and old subgrade, for providing the basis for taking measures to avoid the crack of embankment and disaster of subgrade.

About this research paper

What this paper is about

Based on the crack change and settlement monitoring result of one embankment, this paper gives a conclusion that crack occurring to existing embankment is caused by unbalanced settlements between old embankment and new embankment owing to the outside force during filling newly widened subgrade in combination with theoretic analysis, proposes the suggestion that two aspects, namely materials and depth of subgrade treatment and reinforcing embankment body, should be considered for treatment of connection between new subgrade and old subgrade, for providing the basis for taking measures to avoid the crack of embankment and disaster of subgrade.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Based on the crack change and settlement monitoring result of one embankment, this paper gives a conclusion that crack occurring to existing embankment is caused by unbalanced settlements between old embankment and new embankment owing to the outside force during filling newly widened subgrade in combination with theoretic analysis, proposes the suggestion that two aspects, namely materials and depth of subgrade treatment and reinforcing embankment body, should be considered for treatment of connection between new subgrade and old subgrade, for providing the basis for taking measures to avoid the crack of embankment and disaster of subgrade.

Key concepts: Subgrade, Levee, Settlement (finance), Geotechnical engineering, Human settlement, Engineering, Geology, Forensic engineering

Related papers

Back to paper searchBrowse research topicsOriginal source
ANALYSIS OF INFLUENCE ON POST-CONSTRUCTION SETTLEMENT OF EXISTING EMBANKMENT BY FILLING NEWLY WIDENED SUBGRADE — Research Paper | ScholarLens