2005Yunnan Water PowerRequires access

The Hydraulic Model Test Research on Construction Diversionand Cofferdam Erosion of Xiaowan Hydropower Station

Xiaolin Wang

Open publisher page 0 citations

Abstract

According to the practical conditions and the design indexes of the Xiaowan project the diversion model test was made in study of the influences of the blasting remains and riverbed remains on the discharge capacity of diversion tunnel, the hydraulic scour capacity of diversion tunnel, the velocity distribution of backflow near the cofferdam foot, and erosion characteristic. Also the viable diversion scheme and the corresponding preventive measures were put forward. The diversion model test predicted some potential technical problems, and provided guidance for the construction of the practical project.

About this research paper

What this paper is about

According to the practical conditions and the design indexes of the Xiaowan project the diversion model test was made in study of the influences of the blasting remains and riverbed remains on the discharge capacity of diversion tunnel, the hydraulic scour capacity of diversion tunnel, the velocity distribution of backflow near the cofferdam foot, and erosion characteristic. Also the viable diversion scheme and the corresponding preventive measures were put forward. The diversion model test predicted some potential technical problems, and provided guidance for the construction of the practical project.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

According to the practical conditions and the design indexes of the Xiaowan project the diversion model test was made in study of the influences of the blasting remains and riverbed remains on the discharge capacity of diversion tunnel, the hydraulic scour capacity of diversion tunnel, the velocity distribution of backflow near the cofferdam foot, and erosion characteristic. Also the viable diversion scheme and the corresponding preventive measures were put forward. The diversion model test predicted some potential technical problems, and provided guidance for the construction of the practical project.

Key concepts: Cofferdam, Hydropower, Backflow, Water diversion, Geotechnical engineering, Engineering, Erosion, Rock blasting

Related papers

Back to paper searchBrowse research topicsOriginal source
The Hydraulic Model Test Research on Construction Diversionand Cofferdam Erosion of Xiaowan Hydropower Station — Research Paper | ScholarLens