2006•Yangtze RiverRequires access

RCC dam design of Pengshui hydropower station

Huang Hong-fei

Open publisher page 0 citations

Abstract

Pengshui dam is an arched RCC gravity one with the maximum dam height of 116.5 m.The top openings are designed for flood release and the dam body under the top openings is RCC with its volume of 587.6 thousand m~3,accounting for 58% of total dam concrete volume.The overall RCC economic cross-section is designed for the dam.This paper presents the stress analysis, concrete mix ratio,seepage control scheme and the simplification of dam structure layout.The foundation consolidation grouting with levelled concrete layer plugging is adopted for geologic defect-free position to realize quick RCC construction.

About this research paper

What this paper is about

Pengshui dam is an arched RCC gravity one with the maximum dam height of 116.5 m.The top openings are designed for flood release and the dam body under the top openings is RCC with its volume of 587.6 thousand m~3,accounting for 58% of total dam concrete volume.The overall RCC economic cross-section is designed for the dam.This paper presents the stress analysis, concrete mix ratio,seepage control scheme and the simplification of dam structure layout.The foundation consolidation grouting with levelled concrete layer plugging is adopted for geologic defect-free position to realize quick RCC construction.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Pengshui dam is an arched RCC gravity one with the maximum dam height of 116.5 m.The top openings are designed for flood release and the dam body under the top openings is RCC with its volume of 587.6 thousand m~3,accounting for 58% of total dam concrete volume.The overall RCC economic cross-section is designed for the dam.This paper presents the stress analysis, concrete mix ratio,seepage control scheme and the simplification of dam structure layout.The foundation consolidation grouting with levelled concrete layer plugging is adopted for geologic defect-free position to realize quick RCC construction.

Key concepts: Gravity dam, Consolidation (business), Geotechnical engineering, Hydropower, Foundation (evidence), Engineering, Geology, Roller-compacted concrete

Related papers

Back to paper searchBrowse research topicsOriginal source
RCC dam design of Pengshui hydropower station — Research Paper | ScholarLens