The geological structure of the slope at the right-bank of Longtan Hydropower Station is very complex.It has a large district which was deeply air-slaked and eroded rock-earth.Damage case or potential harm situation have occurred many times and a huge volume of slope slide took place during the course of construction.The cases were under being monitored and predicted to prevent or minimize loss in order to ensure construction activity safety.Now the slope condition trends to be stable according to the analysis of monitoring results after it was improved strength by anchorage cables and piles.

About this research paper

What this paper is about

The geological structure of the slope at the right-bank of Longtan Hydropower Station is very complex.It has a large district which was deeply air-slaked and eroded rock-earth.Damage case or potential harm situation have occurred many times and a huge volume of slope slide took place during the course of construction.The cases were under being monitored and predicted to prevent or minimize loss in order to ensure construction activity safety.Now the slope condition trends to be stable according to the analysis of monitoring results after it was improved strength by anchorage cables and piles.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

The geological structure of the slope at the right-bank of Longtan Hydropower Station is very complex.It has a large district which was deeply air-slaked and eroded rock-earth.Damage case or potential harm situation have occurred many times and a huge volume of slope slide took place during the course of construction.The cases were under being monitored and predicted to prevent or minimize loss in order to ensure construction activity safety.Now the slope condition trends to be stable according to the analysis of monitoring results after it was improved strength by anchorage cables and piles.

Key concepts: Hydropower, Geotechnical engineering, Harm, Geology, Mining engineering, Civil engineering, Environmental science, Engineering