2014Coal Mining TechnologyRequires access

Research on Initial-mining Roof Blasting in Shallow Buried Coal-seam

Lian Zhang

Open publisher page 0 citations

Abstract

In Shendong shallow-buried mining area,hard roof weighting is very strong and roof extensive collapse can result in typhoon in initial mining phrase.This paper analyzed roof disaster reason of shallow buried coal-seam in initial mining phrase,and obtained whether the roof should be forced caved by constructing hanging roof mechanical model for shallow buried coal-seam.The method of determining rational roof caving height was put forward.Field practice showed that the roof control project by this method was feasible and application effect was good.

About this research paper

What this paper is about

In Shendong shallow-buried mining area,hard roof weighting is very strong and roof extensive collapse can result in typhoon in initial mining phrase.This paper analyzed roof disaster reason of shallow buried coal-seam in initial mining phrase,and obtained whether the roof should be forced caved by constructing hanging roof mechanical model for shallow buried coal-seam.The method of determining rational roof caving height was put forward.Field practice showed that the roof control project by this method was feasible and application effect was good.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

In Shendong shallow-buried mining area,hard roof weighting is very strong and roof extensive collapse can result in typhoon in initial mining phrase.This paper analyzed roof disaster reason of shallow buried coal-seam in initial mining phrase,and obtained whether the roof should be forced caved by constructing hanging roof mechanical model for shallow buried coal-seam.The method of determining rational roof caving height was put forward.Field practice showed that the roof control project by this method was feasible and application effect was good.

Key concepts: Roof, Coal mining, Mining engineering, Geology, Rock blasting, Problems in coal mining, Geotechnical engineering, Coal