Study on Cantilever Construction Technology in Long Span Prestressed Concrete Rigid Continuous Compound System Bridge
Tang Chong-guang
Abstract
Tang Chong-guang
Abstract
The full-length of Dongming Yellow River Highway Bridge is 4142.14m.In the meanwhile,the main bridge is a long span prestressed concrete rigid continuous compound system bridge.One long unit of the bridge is 990m and the span of the box beam is 120m.It has particular features such as large scale,complex construction and difficulty.In order to construct the bridge,cantilever construction technology and the main skill craft of the long span prestressed concrete rigid continuous compound system bridge have been given.Following the construction technology,no compulsive folding in 120m of the bridge,altitude error of the folding only 3mm and axial line error only 5mm have been realized.And the cantilever construction cyclic of the box beam is only 6 days.High speed,high precision and safe construction have been achieved.In a word,the cantilever construction technology of the box beam can offer the related data to such bridge's construction.
A significance statement is not available in the OpenAlex record.
A contribution statement is not available in the OpenAlex record.
Method details are not available in the OpenAlex metadata.
Findings are not separately available in the OpenAlex metadata.
Limitations are not available in the OpenAlex metadata.
Application details are not available in the OpenAlex metadata.
The full-length of Dongming Yellow River Highway Bridge is 4142.14m.In the meanwhile,the main bridge is a long span prestressed concrete rigid continuous compound system bridge.One long unit of the bridge is 990m and the span of the box beam is 120m.It has particular features such as large scale,complex construction and difficulty.In order to construct the bridge,cantilever construction technology and the main skill craft of the long span prestressed concrete rigid continuous compound system bridge have been given.Following the construction technology,no compulsive folding in 120m of the bridge,altitude error of the folding only 3mm and axial line error only 5mm have been realized.And the cantilever construction cyclic of the box beam is only 6 days.High speed,high precision and safe construction have been achieved.In a word,the cantilever construction technology of the box beam can offer the related data to such bridge's construction.
Key concepts: Cantilever, Bridge (graph theory), Structural engineering, Box girder, Span (engineering), Beam bridge, Prestressed concrete, Beam (structure)