Ultra-deep Well HA10-1X Cementing Practice

Yan Zhi

Open publisher page 0 citations

Abstract

The well HA 10-1X is located in Northern of Tarim Basin,which some downhole problems are encountered before the first and second stage cementing,such as low formation pressure,lost circulation and long cementing segment,so in this well,the dual thickening time and density cement slurry system and heavy drilling fluid replacement technology are used to reduce operation pressure.In the first stage cementing,the 1.45 g/cm3 and 1.88 g/cm3 cementing slurry is applied in 3,800 m-6,758 m,in the second stage,the 1.45 g/cm3 cementing slurry is used in 0-3,001.64 m.The result of CBL shows that the cementing job quality is qualified,and the cementing quality is improved by this cementing technology.

About this research paper

What this paper is about

The well HA 10-1X is located in Northern of Tarim Basin,which some downhole problems are encountered before the first and second stage cementing,such as low formation pressure,lost circulation and long cementing segment,so in this well,the dual thickening time and density cement slurry system and heavy drilling fluid replacement technology are used to reduce operation pressure.In the first stage cementing,the 1.45 g/cm3 and 1.88 g/cm3 cementing slurry is applied in 3,800 m-6,758 m,in the second stage,the 1.45 g/cm3 cementing slurry is used in 0-3,001.64 m.The result of CBL shows that the cementing job quality is qualified,and the cementing quality is improved by this cementing technology.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

The well HA 10-1X is located in Northern of Tarim Basin,which some downhole problems are encountered before the first and second stage cementing,such as low formation pressure,lost circulation and long cementing segment,so in this well,the dual thickening time and density cement slurry system and heavy drilling fluid replacement technology are used to reduce operation pressure.In the first stage cementing,the 1.45 g/cm3 and 1.88 g/cm3 cementing slurry is applied in 3,800 m-6,758 m,in the second stage,the 1.45 g/cm3 cementing slurry is used in 0-3,001.64 m.The result of CBL shows that the cementing job quality is qualified,and the cementing quality is improved by this cementing technology.

Key concepts: Lost circulation, Petroleum engineering, Slurry, Drilling fluid, Tarim basin, Geology, Cement, Stage (stratigraphy)