Application and Optimization of Horizontal Jet Grouting Piles in Construction of Tunnels in Water-rich Soft Rock Ground

Shi Longyan

Open publisher page 0 citations

Abstract

K15+838.35~+660 section of the trial section of the first phase of line M3 of Qingdao Metro,with 8.15~13.1 m overburden,runs through Grade VI water-rich sand strata.Furthermore,the tunnel section has complex ground surface environment.Therefore,there is great risk in the construction of the tunnel section.However,dewatering and vertical reinforcement can not be executed from the ground surface.Therefore,horizontal jet grouting piles,as well as a series of advance reinforcement technologies are adopted,so as to guarantee the safety of the surface buildings and the tunneling labors.The disadvantage of horizontal jet grouting piles in sand strata and crushed stone strata,i.e.,failure in interlocking,is solved,which guarantees the safety of tunneling in water-rich soft ground.

About this research paper

What this paper is about

K15+838.35~+660 section of the trial section of the first phase of line M3 of Qingdao Metro,with 8.15~13.1 m overburden,runs through Grade VI water-rich sand strata.Furthermore,the tunnel section has complex ground surface environment.Therefore,there is great risk in the construction of the tunnel section.However,dewatering and vertical reinforcement can not be executed from the ground surface.Therefore,horizontal jet grouting piles,as well as a series of advance reinforcement technologies are adopted,so as to guarantee the safety of the surface buildings and the tunneling labors.The disadvantage of horizontal jet grouting piles in sand strata and crushed stone strata,i.e.,failure in interlocking,is solved,which guarantees the safety of tunneling in water-rich soft ground.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

K15+838.35~+660 section of the trial section of the first phase of line M3 of Qingdao Metro,with 8.15~13.1 m overburden,runs through Grade VI water-rich sand strata.Furthermore,the tunnel section has complex ground surface environment.Therefore,there is great risk in the construction of the tunnel section.However,dewatering and vertical reinforcement can not be executed from the ground surface.Therefore,horizontal jet grouting piles,as well as a series of advance reinforcement technologies are adopted,so as to guarantee the safety of the surface buildings and the tunneling labors.The disadvantage of horizontal jet grouting piles in sand strata and crushed stone strata,i.e.,failure in interlocking,is solved,which guarantees the safety of tunneling in water-rich soft ground.

Key concepts: Geotechnical engineering, Dewatering, Overburden, Jet (fluid), Engineering, Groundwater, Roof, Section (typography)

Related papers

Back to paper searchBrowse research topicsOriginal source
Application and Optimization of Horizontal Jet Grouting Piles in Construction of Tunnels in Water-rich Soft Rock Ground — Research Paper | ScholarLens