1974•Unpublished venueRequires access

Temporary support of vertical excavation in weathered sedimentary deposits

K Gillespie

Open publisher page 0 citations

Abstract

During a stage of construction for the Boulcott Street Underpass in the Shell Gully section of the Wellington Urban Motorway, the Contractor, Wilkins and Davies Construction Company Limited, was required and instructed to make a temporary open excavation into a steep hillside slope to provide working space for construction of the western abutment. The site boundary, outside which the Contractor could not operate, was located only 12 feet beyond the back face of the abutment pile cap location. Ground surface level on the boundary ranged up to 50 feet above the proposed base of pile cap level. Thus the flattest open batter slope which could be created was on the order of 1/2 horizontal to 1 vertical.

About this research paper

What this paper is about

During a stage of construction for the Boulcott Street Underpass in the Shell Gully section of the Wellington Urban Motorway, the Contractor, Wilkins and Davies Construction Company Limited, was required and instructed to make a temporary open excavation into a steep hillside slope to provide working space for construction of the western abutment. The site boundary, outside which the Contractor could not operate, was located only 12 feet beyond the back face of the abutment pile cap location. Ground surface level on the boundary ranged up to 50 feet above the proposed base of pile cap level. Thus the flattest open batter slope which could be created was on the order of 1/2 horizontal to 1 vertical.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

During a stage of construction for the Boulcott Street Underpass in the Shell Gully section of the Wellington Urban Motorway, the Contractor, Wilkins and Davies Construction Company Limited, was required and instructed to make a temporary open excavation into a steep hillside slope to provide working space for construction of the western abutment. The site boundary, outside which the Contractor could not operate, was located only 12 feet beyond the back face of the abutment pile cap location. Ground surface level on the boundary ranged up to 50 feet above the proposed base of pile cap level. Thus the flattest open batter slope which could be created was on the order of 1/2 horizontal to 1 vertical.

Key concepts: Excavation, Abutment, Geology, Pile, Section (typography), Geotechnical engineering, Boundary (topology), Mining engineering

Related papers

Back to paper searchBrowse research topicsOriginal source
Temporary support of vertical excavation in weathered sedimentary deposits — Research Paper | ScholarLens