Analysis and monitoring on jacking construction of continuous box girder bridge

Fangyuan Li, Peifeng Wu, Xinfei Yan

Open publisher page 21 citations

Abstract

It is hard to guarantee the strict synchronization of all the jacking-up points in the integral jacking of a large-span continuous box girder bridge. This paper took the Hengliaojing Bridge as background, which need jacking up as an object with 295m length and more than 10,000tons weight, adopted 3D software to calculate the unsynchronized jacking-up working conditions, and studied the relationships between the unsynchronized vertical difference and the girder's deformation behaviour. The aim is to verify the maximum value of the unsynchronized vertical difference, and guide the construction and ensure safety. The monitoring system with its contents is introduced corresponding to the analysis. The results of the deck relative elevations prove that it is difficult to avoid the deck torsional deformation for jacking different; especially the side span shows more deformations for its smaller stiffness. The maximum difference is smaller than the limited value with acceptable stresses in the sections. The jacking heights of the pier in each construction step are controlled regularly according to the design. The shifting of the whole bridge in longitudinal direction is smaller than in transverse direction. The several beginning steps are the key to adjust their support reactions. This study is one parts of the fundamental research for the code "Technical specification for bridge jacking-up and reposition of China". The whole synchronous jacking project of the main bridge set a world record by the World Record Association for the whole bridge jacking project with the longest span of the world.

About this research paper

What this paper is about

It is hard to guarantee the strict synchronization of all the jacking-up points in the integral jacking of a large-span continuous box girder bridge. This paper took the Hengliaojing Bridge as background, which need jacking up as an object with 295m length and more than 10,000tons weight, adopted 3D software to calculate the unsynchronized jacking-up working conditions, and studied the relationships between the unsynchronized vertical difference and the girder's deformation behaviour. The aim is to verify the maximum value of the unsynchronized vertical difference, and guide the construction and ensure safety. The monitoring system with its contents is introduced corresponding to the analysis. The results of the deck relative elevations prove that it is difficult to avoid the deck torsional deformation for jacking different; especially the side span shows more deformations for its smaller stiffness. The maximum difference is smaller than the limited value with acceptable stresses in the sections. The jacking heights of the pier in each construction step are controlled regularly according to the design. The shifting of the whole bridge in longitudinal direction is smaller than in transverse direction. The several beginning steps are the key to adjust their support reactions. This study is one parts of the fundamental research for the code "Technical specification for bridge jacking-up and reposition of China". The whole synchronous jacking project of the main bridge set a world record by the World Record Association for the whole bridge jacking project with the longest span of the world.

Why it matters

OpenAlex reports 21 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

It is hard to guarantee the strict synchronization of all the jacking-up points in the integral jacking of a large-span continuous box girder bridge. This paper took the Hengliaojing Bridge as background, which need jacking up as an object with 295m length and more than 10,000tons weight, adopted 3D software to calculate the unsynchronized jacking-up working conditions, and studied the relationships between the unsynchronized vertical difference and the girder's deformation behaviour. The aim is to verify the maximum value of the unsynchronized vertical difference, and guide the construction and ensure safety. The monitoring system with its contents is introduced corresponding to the analysis. The results of the deck relative elevations prove that it is difficult to avoid the deck torsional deformation for jacking different; especially the side span shows more deformations for its smaller stiffness. The maximum difference is smaller than the limited value with acceptable stresses in the sections. The jacking heights of the pier in each construction step are controlled regularly according to the design. The shifting of the whole bridge in longitudinal direction is smaller than in transverse direction. The several beginning steps are the key to adjust their support reactions. This study is one parts of the fundamental research for the code "Technical specification for bridge jacking-up and reposition of China". The whole synchronous jacking project of the main bridge set a world record by the World Record Association for the whole bridge jacking project with the longest span of the world.

Key concepts: Jacking, Structural engineering, Bridge (graph theory), Span (engineering), Engineering, Deck, Stiffness, Geotechnical engineering

Related papers

Back to paper searchBrowse research topicsOriginal source
Analysis and monitoring on jacking construction of continuous box girder bridge — Research Paper | ScholarLens