Geological and geotechnical assessment for an underground powerhouse and recommended support system, Chamera Hydroelectric Project, stage-II, H.P.

Anil K. Sood, Brijes Mishra

Open publisher page 0 citations

Abstract

Chamera H.E. Project, Stage-II, H.P. marks a milestone in the history of development of hydropower in India being the first of its kind where all civil works were completed within three and a half year duration. The project is housed in a domain of phyllites/phyllitic quartzites & quartzites of Chamba Formation. An underground powerhouse, located in the right bank of river Ravi is designed to generate 300 MW (3×100) of power. The underground cavern was aligned in N30°E-S30°W direction taking the geological environment into account. Adequate support measures including high tensile Dywidag rock bolts were provided, taking into consideration the expected rock stresses. The paper outlines the geological suitability for the underground structure, the optimum support system of rock bolts on the basis of geological conditions.

About this research paper

What this paper is about

Chamera H.E. Project, Stage-II, H.P. marks a milestone in the history of development of hydropower in India being the first of its kind where all civil works were completed within three and a half year duration. The project is housed in a domain of phyllites/phyllitic quartzites & quartzites of Chamba Formation. An underground powerhouse, located in the right bank of river Ravi is designed to generate 300 MW (3×100) of power. The underground cavern was aligned in N30°E-S30°W direction taking the geological environment into account. Adequate support measures including high tensile Dywidag rock bolts were provided, taking into consideration the expected rock stresses. The paper outlines the geological suitability for the underground structure, the optimum support system of rock bolts on the basis of geological conditions.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Chamera H.E. Project, Stage-II, H.P. marks a milestone in the history of development of hydropower in India being the first of its kind where all civil works were completed within three and a half year duration. The project is housed in a domain of phyllites/phyllitic quartzites & quartzites of Chamba Formation. An underground powerhouse, located in the right bank of river Ravi is designed to generate 300 MW (3×100) of power. The underground cavern was aligned in N30°E-S30°W direction taking the geological environment into account. Adequate support measures including high tensile Dywidag rock bolts were provided, taking into consideration the expected rock stresses. The paper outlines the geological suitability for the underground structure, the optimum support system of rock bolts on the basis of geological conditions.

Key concepts: Hydroelectricity, Rock bolt, Hydropower, Stage (stratigraphy), Engineering, Milestone, Mining engineering, Civil engineering

Related papers

Back to paper searchBrowse research topicsOriginal source
Geological and geotechnical assessment for an underground powerhouse and recommended support system, Chamera Hydroelectric Project, stage-II, H.P. — Research Paper | ScholarLens